DIS - Case Record for 94-0051-GA-UNC Skip to main content

Case Record For:

94-0051-GA-UNC

File a Public Comment
Case Title: CINCINNATI GAS & ELECTRIC COMPANY
Status: AR-Archived
Industry Code: GA-GAS
Purpose Code: UNC-Unclassified
Date Opened: 1/13/1994
Date Closed: 7/14/1994
Printable Docket Card Service List
View per page
Date FiledSummaryPages
08/08/1994Tariff, PUCO No. 18, sheet 11.18, sheet 73, and sheet 74, filed on behalf of applicant by W. Ginn.0
07/19/1994Correspondence letter opposing the application, filed by G. Pierce, Pierce Economics.0
07/14/1994Finding & Order approving and adopting the stipulation in its entirety; that CG&E comply with all the terms of the stipulation; that CG&E's previously-approved transportation contracts for on-system transportation customers are amended to include the transition costs surcharge set forth in the stipulation, unless such contract expressly provides other- wise; that CG&E's proposed tariff is approved.0
07/07/1994Tariff, PUCO No. 18, sheets 73 and 74, filed on behalf of applicant by J. Banner.0
05/26/1994Transcript filed for hearing held 5/17/94, (MKF), 12 pgs., Submitted.0
05/23/1994Correspondence letter opposing the application, filed by D. Salisbury.0
05/17/1994Comments filed by D. Sallsbury, CG&E residential customer.0
05/17/1994Proofs of publication filed. (Hamilton, Clermont, Preble, Brown, , Highland, Butler, Adams, Warren, and Clinton Counties)0
04/13/1994Entry denying the motion for approval of the stipulation without hearing; scheduling a hearing at 10:00 a.m. on 5/17/94 at the Commission offices; that CG&E publish notice of the hearing. (AE)0
01/13/1994Joint motion and memorandum in support for approval of application without hearing, filed on behalf of applicant by J. Banner; OCC by M. Samuels; Armco Steel Company, L.P. by D. Boehm; and IEC by L. Bell.0
01/13/1994In the matter of the application of The Cincinnati Gas & Electric Company and attached stipulation and recommendation for approval of a stipulation and recommendation addressing the recovery of pipeline transition costs arising from FERC Order 636.0