Date Filed | Summary | Pages |
05/19/2021 | Mitchell Ave Pole Replacement Project Notification of Completion of Construction and In-Service Date electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
05/21/2020 | Service Notice. | 2 |
05/21/2020 | Opinion & Order approving the accelerated applications in the above-captioned proceedings for certificates to construct various transmission line projects and for a natural gas pipeline reroute project. electronically filed by Ms. Mary E Fischer on behalf of Ohio Power Siting Board. | 8 |
04/23/2020 | Notice of Letter of Acceptance of required condition for the Mitchell Ave. Pole Replacement Project electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
04/16/2020 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 5 |
04/16/2020 | Service Notice | 2 |
04/09/2020 | Duke Energy Ohio, Inc.'s Response to Staff Data Request 01-001 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. | 2 |
01/29/2020 | Proof of Service for the Mitchell Ave Pole Replacement Project electronically filed by Carys Cochern on behalf of Duke Energy. | 10 |
01/23/2020 | Construction Notice Application for the Mitchell Ave Pole Replacement Project electronically filed by Carys Cochern on behalf of Duke Energy. | 28 |
01/16/2020 | In the matter of the Pre-application notification letter for the Mitchell Ave Pole Replacement Project electronically filed by Carys Cochern on behalf of Duke Energy. | 2 |