DIS - Case Record for 15-0288-EL-BNR Skip to main content
      
      
CASE NUMBER: 15-0288-EL-BNR
CASE DESCRIPTION: Avon-Beaver No1 and No2 345kV Transmission Line Extensions to Lake Avenue Substation
DOCUMENT SIGNED ON: 4/30/2024
DATE OF SERVICE: ________________________________________
12/05/2016 Construction Notice that project was completed on November 30, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
03/21/2016 Notice that construction on the Avon-Beaver No.1 and No.2 345 kV Transmission Line Extensions to Lake Avenue Substation Project was approved by the Board on May 13, 2015, commenced on March 11, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
05/06/2015 Staff Report of Investigation electronically filed by Mrs. Yvonne W. Cooper on behalf of Staff of OPSB.
04/01/2015 Construction notice of American Transmission System Incorporated for Avon-Beaver No. l and No. 2 345 kV Transmission Line Extensions to Lake Avenue Substation Project filed by N. Bryksenkova.
03/31/2015 In the matter of the Notification of Construction (Construction Notice) for the Avon-Beaver No 1 and No 2 345 kv Transmission Line Extensions to Lake Avenue Substation electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.