Date Filed | Summary | Pages |
07/18/2019 | Case Action Form Closing Case effective 7/18/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. | 2 |
08/03/2017 | Correspondence stating that construction has been completed as of July 28, 2017 filed on behalf of FirstEnergy Service Company by N. Bryksenkova. | 1 |
02/17/2017 | Correspondence regarding typographical error in the document previously filed on 2/13/17 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
02/13/2017 | Construction Notice that project commenced on February 15, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. | 1 |
10/07/2016 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 4 |
09/01/2016 | Construction Notice for Hanna-Shalersville 138 kV Transmission Line Structure #12229 Replacement Project filed by Nataliya Bryksenkova on behalf of FirstEnergy Serivice Company. | 57 |
08/18/2016 | In the matter of the Pre-Application Notification Letter for the Hanna-Shalersville 138 kV Transmission Line Structure #12229 Replacement Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 2 |