07/18/2019
|
Case Action Form Closing Case effective 7/18/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. |
08/03/2017
|
Correspondence stating that construction has been completed as of July 28, 2017 filed on behalf of FirstEnergy Service Company by N. Bryksenkova. |
02/17/2017
|
Correspondence regarding typographical error in the document previously filed on 2/13/17 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. |
02/13/2017
|
Construction Notice that project commenced on February 15, 2016 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. |
10/07/2016
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
09/01/2016
|
Construction Notice for Hanna-Shalersville 138 kV Transmission Line Structure #12229 Replacement Project filed by Nataliya Bryksenkova on behalf of FirstEnergy Serivice Company. |
08/18/2016
|
In the matter of the Pre-Application Notification Letter for the Hanna-Shalersville 138 kV Transmission Line Structure #12229 Replacement Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |