Date Filed | Summary | Pages |
05/11/2005 | Letter to OPSB that construction on project was started on October 25, 2004, completed and energized on April 18, 2005, filed on behalf of applicant by J. Heppner. | 1 |
12/11/2003 | Response to Letter of Notification and investigation report approving the Letter of Notification, filed by K. Lambeck, PUCO staff. | 2 |
11/25/2003 | Notice of intervention and affidavit in support, filed on behalf of the City of Dublin, Ohio by G. Dunn. | 7 |
10/27/2003 | In the matter of the application of American Electric Power hereby submits a letter of notification for the Dublin-Sawmill 138 kV line, relocation at Sawmill Station project. Heppner, John R. filed on behalf of American Electric Power Co.. | 18 |
|