CASE NUMBER: 03-2182-EL-BLN
CASE DESCRIPTION: AMERICAN ELECTRIC POWER /DUBLIN-SAWMILL 138kV LINE
DOCUMENT SIGNED ON: 4/25/2024
DATE OF SERVICE: ________________________________________
05/11/2005 Letter to OPSB that construction on project was started on October 25, 2004, completed and energized on April 18, 2005, filed on behalf of applicant by J. Heppner.
12/11/2003 Response to Letter of Notification and investigation report approving the Letter of Notification, filed by K. Lambeck, PUCO staff.
11/25/2003 Notice of intervention and affidavit in support, filed on behalf of the City of Dublin, Ohio by G. Dunn.
10/27/2003 In the matter of the application of American Electric Power hereby submits a letter of notification for the Dublin-Sawmill 138 kV line, relocation at Sawmill Station project. Heppner, John R. filed on behalf of American Electric Power Co..