Summary: |
Entry ordering that NS submit to the Commission and ORDC site plans and cost estimates for the projects by March 22, 2011; by March 29, 2011, NS file a notice in this docket advising that it has submitted site plans and cost estimates to the Commission and ORDC; by April 21,2011, NS file a notice that it has initiated with AEP the process to ensure that electric service will be available at the involved grade crossings as set forth in finding 4. |
|