Summary: |
Finding and Order stating that by August 26,2017, NS file notice that it has initiated with DP&L, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossings as set forth in Paragraph 8; NS follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the projects by July 26,2018. |
|