DIS - Case Record for 99-0541-GA-BTX Skip to main content
      
      
CASE NUMBER: 99-0541-GA-BTX
CASE DESCRIPTION: NORTHEAST OHIO NAT GAS/WEST LORAIN
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
11/10/2003 A letter report summarizing the findings of the 2-year post construction wetland impact evaluation conducted by URS Corporation (URS) on 10/7/03 for the West Lorain Natural Gas Pipeline project filed on behalf of applicant by T. Krauss.
11/10/2003 Letter report summarizing the findings of the two-year post-construction wetland impact evaluation conducted by URS Corporation on 10/7/2003 for the West Lorain Natural Gas Pipeline filed on behalf of applicant by A. Hale.
01/23/2003 service notice filed.
01/21/2003 Entry ordering that the certificates and approvals listed herein and previously granted to Northeast Ohio Natural Gas Corp., Ohio Edison Company, and Mid-Atlantic Energy Development Co. for the construction and operation of the described electric facilities and natural gas pipelines shall be transferred to Generation; that, as a result of these transfers, Generation shall be bound by and comply with all terms and conditions of these certificates and approvals. (OPSB)
10/24/2002 Application to transfer certain certificates of environmental compatibility and public need and certain letters of notification to FirstEnergy Corp. filed by C. Schraff.
09/17/2001 Letter stating that construction of the West Lorain Natural Gas Pipeline was completed on September 5, 2001, filed on behalf of applicant by T. Krauss.
06/29/2001 Letter stating that applicant began commercial operation on May 25, 2001, filed by T. Krauss.
02/26/2001 Follow-up report for the hydrostatic test conducted on the West Lorain Natural Gas Pipeline on December 14, 19, and 20, 2000, filed on behalf of applicant by T. Krauss.
01/02/2001 Construction drawings filed on behalf of applicant.
12/22/2000 Additional information filed on behalf of applicant by T. Krauss.
12/18/2000 Response filed on behalf of applicant by H. Griset.
10/26/2000 ICN #0055 Additional information filed on behalf of appli- cant by T. Krauss. (3 pgs.)
10/05/2000 ICN #0054 Several permit documents filed on behalf of appli- cant by T. Krauss. (97 pgs.)
09/26/2000 ICN #0052 Construction drawings and text portion of the Storm Water Pollution Prevention Plan, filed on behalf of applicant by T. Krauss. (2 pgs.)
09/26/2000 ICN #0053 Two prints of a drawing illustrating the end connections and mainline valve station for this project, filed by D. Cooper, P.E. (2 pgs.)
09/22/2000 ICN #0051 Correspondence to Mr. Thomas C. Burgess, First- Energy Corp., regarding the engineering drawings submitted on September 15, 2000, filed by K. Wissman, PUCO staff. (1 pg.)
09/11/2000 ICN #0049 Copy of the August 10, 2000 letter from the Ohio EPA regarding hydrostatic test water release on the project, filed on behalf of applicant by T. Krauss. (2 pgs.)
09/11/2000 ICN #0050 Copy of the August 18, 2000 letter from the Ohio EPA regarding coverage for the project under Ohio EPA Storm Water General Permit Number: OHR109461, filed on behalf of applicant by T. Krauss. (9 pgs.)
09/06/2000 Notice of Intent (NOI) application, Ohio EPA's General Storm Water Permit, West Lorain Natural Gas Pipeline Project located in Lorain County. Filed by S. Brown (5 pgs) (FILED 9/5/00)
09/06/2000 Environmental Construction Standards (66 pgs) (FILED 9/5/00)
09/06/2000 Letter regarding the Ohio Environmental Protection Agency has received the Notice of Intent (NOI) for coverage under the Storm Water General permit for construction activity West Lorain Natural Gas Pipeline Project. Filed by C. Jones (FILED 9/5/00)
08/25/2000 ICN No. 0045, Copy of each Federal or State permit or authorization for the project, filed on behalf of applicant by T. Krauss.
08/25/2000 ICN #0045 Copy of each Federal or State permit or authori- zation for the project, filed on behalf of applicant by T. Krauss. (6 pgs.)
07/17/2000 ICN #0043 Wetland Delineation Report filed on behalf of applicant. (89 pgs.)
07/17/2000 ICN #0044 Opinion, Order and Certificate ordering that certificate of environmental compatibility and public need for the construction, operation, and maintenance of West Lorain Natural Gas Pipeline project be issued; that the certificate contain the conditions set forth in the stipulation filed by the Board Staff and Northeast. (22 pgs.)
07/17/2000 ICN #0043 Wetland Delineation Report filed on behalf of applicant. (89 pgs.)
07/17/2000 ICN #0044 Opinion, Order and Certificate ordering that certificate of environmental compatibility and public need for the construction, operation, and maintenance of West Lorain Natural Gas Pipeline project be issued; that the certificate contain the conditions set forth in the stipulation filed by the Board Staff and Northeast. (22 pgs.)
07/06/2000 ICN #0042 Additional information filed on behalf of appli- cant by H. Griset. (1 pg.)
07/06/2000 ICN #0042 Additional information filed on behalf of applicant by H. Griset. (1 pg.)
07/05/2000 ICN #0041 Transcript filed for hearing held 6/21/00, (GS), 9 pgs., Submitted. (PUCO-Columbus, OH)
07/05/2000 ICN #0041 Transcript filed for hearing held 6/21/00, (GS), 9 pgs., Submitted. (PUCO-Columbus, OH)
06/29/2000 ICN #0039 Correspondence regarding the application, filed by D. Urig, Amherst Township Trustee. (6 pgs.)
06/29/2000 Correspondence letter opposing the application, filed on behalf of Amherst Township by D. Urig.
06/29/2000 ICN #0040 Transcript filed for hearing held 6/15/00, (SD), 6 pgs., Con't. (PUCO-Columbus, OH)
06/29/2000 ICN #0039 Correspondence regarding the application, filed by D. Urig, Amherst Township Trustee. (6 pgs.)
06/29/2000 ICN #0040 Transcript filed for hearing held 6/15/00, (SD), 6 pgs., Con't. (PUCO-Columbus, OH)
06/28/2000 ICN #0038 Joint stipulation and recommended findings of fact and conclusions of law filed on behalf of the PUCO staff by W. Wright and M. Malone; and applicant by C. Schraff. (23 pgs.)
06/28/2000 ICN #0038 Joint stipulation and recommended findings of fact and conclusions of law filed on behalf of the PUCO staff by W. Wright and M. Malone; and applicant by C. Schraff. (23 pgs.)
06/27/2000 ICN #0037 Transcript filed for hearing held 6/13/00, (GS), 113 pgs. (Lorain, Ohio)
06/23/2000 ICN #0036 Entry denying Amherst Township's motion to con- tinue the hearing. (AE) (2 pgs.)
06/23/2000 ICN #0036 Entry denying Amherst Township's motion to continue the hearing. (AE) (2 pgs.)
06/22/2000 ICN #0037 Transcript filed for hearing held 6/13/00, (GS), 113 pgs. (Lorain, Ohio)
06/22/2000 ICN #0035 Route and property map filed on behalf of First- Energy Corp. by G. Cunningham. (2 pgs.)
06/22/2000 ICN #0035 Route and property map filed on behalf of FirstEnergy Corp. by G. Cunningham. (2 pgs)
06/21/2000 ICN #0034 Correction to the staff report docketed on May 26, 2000, filed on behalf of the PUCO staff by W. Wright. (1 pg.)
06/21/2000 ICN #0034 Correction to the staff report docketed on May 26, 2000, filed on behalf of the PUCO staff by W. Wright. (1 pg.)
06/19/2000 ICN #0033 Memorandum in opposition to motion by Amherst Township to continue adjudicatory hearing, filed on behalf of applicant by C. Schraff. (3 pgs.)
06/19/2000 ICnN #0032 Motion for immediate consideration of motion to continue adjudicatory hearing and motion to continue hearing filed on behalf of the Board of Trustees of Amherst Township by G. Innes. (5 pgs.)
06/19/2000 ICN #0032 Motion for immediate consideration of motion to continue adjudicatory hearing and motion to continue hearing filed on behalf of the Board of Trustees of Amherst Township by G. Innes. (5 pgs.)
06/19/2000 ICN #0033 Memorandum in opposition to motion by Amherst Township to continue adjudicatory hearing, filed on behalf of applicant by C. Schraff. (3 pgs.)
06/12/2000 ICN #0031 Response letter to previously filed corres- pondence from Mr. Gary Saathoff, filed by K. Wissman, PUCO staff. (1 pg.)
06/12/2000 ICN #0031 Response letter to previously filed correspondence from Mr. Gary Saathoff, filed by K. Wissman, PUCO staff. (1 pg.)
06/09/2000 ICN #0030 Entry granting Amherst Township's motion to intervene; that the adjudicatory hearing be continued to 10:00 a.m., on June 21, 2000, at the Commission offices. (AE) (2 pgs.)
06/09/2000 ICN #0030 Entry granting Amherst Township's motion to intervene; that the adjudicatory hearing be continued to 10:00 a.m., on June 21, 2000, at the Commission offices. (AE) (2 pgs.)
06/07/2000 Correspondence dated June 5, 2000, regarding the application filed by G. Saathoff. (3 pgs.)
06/07/2000 ICN #0028 Correspondence dated June 7, 2000, regarding the application, filed by G. Saathoff. (1 pg.)
06/07/2000 ICN # 29 Correspondence dated June 5, 2000, regarding the application filed by G. Saathoff. (3 pgs.)
06/07/2000 ICN #0028 Correspondence dated June 7, 2000, regarding the application, filed by G. Saathoff. (1 pg.)
06/05/2000 INC #0027 Response letter to Mr. Gary Saathoff's corres- pondence letter dated May 24, 2000, filed by J. McNaughton, PUCO staff. (1 pg.)
06/05/2000 ICN #0026 Response letter to Mr. Gary Saathoff's corres- pondence letter dated May 22, 2000, filed by J. McNaughton, PUCO staff. (1 pg.)
06/05/2000 ICN #0025 Response letter to Mr. Gary Saathoff's corres- pondence letter dated May 25, 2000, filed by J. McNaughton, PUCO staff. (1 pg.)
06/02/2000 ICN #0024 Proofs of Publication filed on behalf of applicant by C. Schraff. (9 pgs.) (Ashtabula, Guauga, Lake, Lorain, Medina, Portage, Summit, and Trumbull Counties
06/02/2000 ICN #0024 Proofs of Publication filed on behalf of applicant by C. Schraff. (9 pgs.) (Ashtabula, Guauga, Lake, Lorain, Medina, Portage, Summit, and Trumbull Counties)
05/26/2000 ICN #0022 Additional information filed on behalf of applicant by T. Burgess. (8 pgs.)
05/26/2000 Staff Report filed.
05/26/2000 ICN #0023 Staff Report filed. (32 pgs.)
05/26/2000 ICN #0022 Additional information filed on behalf of appli- cant by T. Burgess. (8 pgs.)
05/26/2000 Service Notice
05/18/2000 ICN #0021 Additional information filed on behalf of appli- cant by H. Griset. (2 pgs.)
05/18/2000 ICN #0021 Additional information filed on behalf of applicant by H. Griset. (2 pgs.)
05/15/2000 ICN #0020 Response letter to Mr. Gary Saathoff, filed by K. Wissman, PUCO staff. (1 pg.)
05/15/2000 ICN #0019 Correspondence letter regarding the application, filed by Gary Saathoff. (1 pg.)
05/15/2000 ICN #0020 Response letter to Mr. Gary Saathoff, filed by K. Wissman, PUCO staff. (1 pg.)
05/15/2000 ICN #0019 Correspondence letter regarding the application, filed by Gary Saathoff. (1 pg.)
05/08/2000 ICN #0018 Notice of intervention filed on behalf of the Board of Trustees of Amherst Township by G. Innes. (6 pgs.) (FILED 5/5/00 AND INCORRECTLY PUT INTO CASE NO. 00-541-TP-AEC)
05/05/2000 ICN #0018 Notice of intervention filed on behalf of the Board of Trustees of Amherst Township by G. Innes. (6 pgs.)
04/26/2000 Entry scheduling a public hearing at 7:00 p.m. on June 13, 2000, in Lorain, Ohio; scheduling an adjudicatory hearing at 10:00 a.m., on June 15, 2000, at the Commission offices. (AE) (2 pgs.)
04/26/2000 Entry scheduling a public hearing at 7:00 p.m. on June 13, 2000, in Lorain, Ohio; scheduling an adjudicatory hearing at 10:00 a.m., on June 15, 2000, at the Commission offices. (AE) (2 pgs.)
04/17/2000 ICN #0016 Proof of Service filed on behalf of applicant by C. Schraff. (34 pgs.)
04/17/2000 ICN #0016 Proof of Service filed on behalf of applicant by C. Schraff. (34 pgs.)
04/11/2000 ICN #0015 Correspondence letter to Mr. Thomas C. Burgess, FirstEnergy Corp, filed on behalf of the PUCO staff. (2 pgs.)
04/11/2000 ICN #0015 Correspondence letter to Mr. Thomas C. Burgess, FirstEnergy Corp, filed on behalf of the PUCO staff. (2 pgs
02/28/2000 ICN #0014 Entry ordering that the applicant's request for Staff to resume their review of the application is granted in accordance with Finding 4. (AE) (2 pgs.)
02/28/2000 ICN #0014 Entry ordering that the applicant's request for Staff to resume their review of the application is granted in accordance with Finding 4. (AE) (2 pgs.)
02/25/2000 ICN #0013 Two (2) sets of route and property maps for this project, filed on behalf of applicant by C. Schraff. (12 pgs.)
02/25/2000 ICN #0013 Two (2) sets of route and property maps for this project, filed on behalf of applicant by C. Schraff. (12 pgs.)
01/21/2000 ICN #0012 Correspondence letter to Kim Wissman, PUCO staff, filed on behalf of applicant by C. Schraff. (3 pgs.)
01/21/2000 ICN #0012 Correspondence letter to Kim Wissman, PUCO staff, filed on behalf of applicant by C. Schraff. (3 pgs.)
10/12/1999 ICN #0011 Response filed on behalf of FirstEnergy Corp. by G. Cunningham. (6 pgs.)
09/22/1999 ICN #0010 Entry ordering that the applicants' motion for Staff to resume their review of the application filed in 99-540 and the notification filed in 99-736 is granted; that the applicants' motion to indefinitely suspend review of the application filed in 99-541 is granted until the Board specifically orders otherwise. (AE) (2 pgs.)
09/21/1999 ICN #0009 Corrected certificate of service filed on behalf of applicant by C. Schraff. (2 pgs.)
09/13/1999 ICN #0008 Corrected certificate of service filed on behalf of applicant by C. Schraff. (2 pgs.)
09/10/1999 Motion for Continuance and Extension of time pursuant to Northeast Ohio Natural Gas/West Lorain filed by C. Schraff (6pgs)
08/06/1999 ICN #0006 Entry ordering that FirstEnergy's request for Staff to suspend their review of the applications and notification is granted. (AE) (2 pgs.)
08/02/1999 ICN #0005 Motion for continuance and extension of time pursuant to OAC 4906-7-13 and memorandum in support filed on behalf of applicants by C. Schraff and M. Beiting. (4 pgs.)
08/02/1999 ICN #0005 Motion for continuance and extension of time pursuant to OAC 4906-7-13 and memorandum in support filed on behalf of applicants by C. Schraff and M. Beiting. (4 pgs.)
06/24/1999 ICN #0004 Notice of appearance filed on behalf of the PUCO staff by W. Wright; and the Attorney General of Ohio's office by M. Idzkowski. (2 pgs.)
06/17/1999 ICN #0003 Application filed on behalf of applicant by T. Burgess. (FILED 6/16/99)
06/11/1999 ICN #0002 Entry ordering that Ohio Edison's requests to waiver the requirements that the application be filed with the Board at least two years prior to the commencement of construction of a major utility facility, and the require- ment to file fully developed information on an alternative site are granted; that Northeast's request to waive the requirement that two rights of ways shall not be considered as alternatives if they share more than twenty percent of the rights-of-way in common is granted. (AE) (3 pgs.)
04/30/1999 ICN #0001 In the matter of the motion for waiver of North- east Ohio Natural Gas regarding the West Lorain Combustion Turbine Project. (66 pgs.)