05/13/1998 | Entry closing this case of record. (1 pg.) | 1 |
04/29/1998 | Final report submitted on behalf of the PUCO staff by B. Johrendt. (3 pgs.) | 3 |
09/18/1997 | Entry ordering that the site plans and costs estimates submitted by CSX be approved and that CSX complete the project as quickly as possible, but in any event not later than June 1998. (AE) (2 pgs.) | 2 |
09/17/1997 | Findings and recommendations filed by B. Johrendt, PUCO staff. (25 pgs.) | 25 |
05/15/1997 | Entry ordering that the stipulation and recommendation sub- mitted by the parties be approved; that CSX Transportation submit, within 90 days of the date of this entry, project site plans and costs estimates for Commission approval; that the Village of Ottawa and any other governmental entities having jurisdiction of the roadways at the project crossings be hereby advised of the Commission funding available for supplemental improvements at such crossings and the appli cation procedure as set forth in Finding 4. (3 pgs.) | 3 |
04/24/1997 | Subsidy agreement filed on behalf of CSX Transportation by R. Beckham; PUCO staff by A. Agler; Village of Ottawa by K. Maag and H. Schierloh. (9 pgs.) | 9 |
03/07/1997 | In the matter of a request of the installation of active warning devices at 11th Street (155-726N) and 4th Street (155-724A), Village of Ottawa, Putnam County, CSX Trans- poration Co. (6 pgs.) | 6 |