CASE NUMBER: 94-2028-EL-BLN
CASE DESCRIPTION: TOLEDO EDISON/COMMERCIAL COOKWARE
DOCUMENT SIGNED ON: 4/16/2024
DATE OF SERVICE: ________________________________________
01/19/2001 Memo closing this case of record.
09/06/1995 ICN #0005 Letter stating that construction on this project was completed and the line was energized on March 31, 1995, filed on behalf of applicant by T. Denzler. (1 pg.)
03/16/1995 ICN #0004 Letter informing the Commission that the planned date of initial construction on this project is the week of March 15, 1995, filed on behalf of applicant by T. Denzler. (1 pg.)
02/07/1995 ICN #0003 Letter in response to Letter of Notification, filed by K. Wissman, OPSB staff. (1 pg.)
02/06/1995 ICN #0002 Investigation report approving the Letter of Notification, filed on behalf of the OPSB staff by J. O'Dell. (1 pg.)
12/22/1994 ICN #0001 In the matter of the Letter of Notification of Toledo Edison Company covering the installation of a 138kV transmission line tap to service a mobile substation, Commerical Cookware, that will be istalled when needed. (14 pgs.)