Date Filed | Summary | Pages |
08/30/1990 | Entry dismissing case. | 0 |
08/06/1990 | Motion to dismiss filed on behalf of the respondent by D. Hogan. | 0 |
07/03/1990 | Entry ordering parties to comply with the informal agreement reached at the prehearing conference. (AE) | 0 |
06/18/1990 | Testimony of Barry Ringle filed on behalf of respondent by D. Hogan. | 0 |
06/18/1990 | Testimony of Clarence Hartzell filed on behalf of respondent by D. Hogan. | 0 |
06/13/1990 | Motion to amend answer and amendment to answer filed on behalf of respondent by D. Hogan. | 0 |
06/08/1990 | Proof of Publication filed. (Defiance County) | 0 |
05/22/1990 | Legal notice sent to the Defiance Cresent (Defiance County). | 0 |
05/15/1990 | Entry denying respondent's request to dismiss this complaint and scheduling a prehearing conference at 10:00 a.m. on June 26, 1990 at the Commission. Also scheduling a hearing on June 26, 1990 at 1:30 p.m. at the offices of the PUCO. | 0 |
03/20/1990 | Answer filed on behalf of respondent by D. Hogan. | 0 |
03/01/1990 | Complaint letter and copy of complaint mailed to: Toledo Edison Company, Office of the president, Toledo, OH. | 0 |
02/28/1990 | In the matter of the complaint of William R. Hageman (vs) Toledo Edison Company relative to the alleged inadequate wiring of electricity. | 0 |