DIS - Case Record for 23-0891-EL-AEC Skip to main content
      
      
CASE NUMBER: 23-0891-EL-AEC
CASE DESCRIPTION: In the Matter of the Application of Ohio Power Company and New Albany Data Center, LLC for Approval of a Reasonable Arrangement Under R.C. 4905.31 and
DOCUMENT SIGNED ON: 5/13/2024
DATE OF SERVICE: ________________________________________
03/18/2024 Ohio Power Company Notice of Withdrawal of Counsel, Matthew S. McKenzie electronically filed by Mr. Steven T. Nourse on behalf of Ohio Power Company.
02/07/2024 Service Notice.
02/07/2024 Finding & Order that the Commission finds that the application for a reasonable arrangement between Ohio Power Company and New Albany Data Center, LLC is reasonable and should be approved electronically filed by Ms. Donielle M. Hunter on behalf of Public Utilities Commission of Ohio.
12/07/2023 Staff Review and Recommendation regarding the Joint Application of Ohio Power Company and New Albany Data Center, LLC, for approval of a Reasonable Arrangement electronically filed by Zee Molter on behalf of PUCO Staff.
09/28/2023 In the Matter of the Joint Application of Ohio Power Company and New Albany Data Center, LLC for a reasonable arrangement to support the Silicon Heartland Data Center Campus electronically filed by Mr. Steven T. Nourse on behalf of Ohio Power Company.