12/07/2023
|
Correspondence Proof of Compliance with Condition (2). electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
12/07/2023
|
Correspondence Proof of Compliance with Condition (5). electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
10/11/2023
|
Notice of Start of Construction electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
09/21/2023
|
Service Notice - Staff Report. |
09/21/2023
|
Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB. |
09/07/2023
|
Response to Staff's 2nd Set of Data Request electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
06/30/2023
|
Construction Notice Application for the Hartman Farms 138 kV Extension No. 6 Transmission Line Project Phase 2 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
06/29/2023
|
In the Matter of the Pre-application Notification Letter for the Hartman Farms 138 kV Extension No. 6 Transmission Line Project (Phase 2) electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |