09/20/2023
|
Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
09/18/2023
|
Notification of Start of Construction-Anguin 138 kV Extension No. 2 and No. 3 Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
08/31/2023
|
Service Notice - Staff Report. |
08/31/2023
|
Staff Report of Investigation electronically filed by Mark C. Bellamy on behalf of OPSB Staff. |
06/09/2023
|
Letter of Notification of Application for n for Anguin 138 kV Extension No. 2 and No. 3 Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
06/08/2023
|
In the Matter of the Pre-application Letter electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |