Date Filed | Summary | Pages |
01/08/2024 | Start of Construction notice electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 2 |
01/08/2024 | Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. | 175 |
05/12/2023 | Service Notice - Staff Report. | 2 |
05/12/2023 | Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB. | 6 |
04/06/2023 | Responses to Staff's 4th Set electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 90 |
04/04/2023 | Response to Ohio Power Siting Board Staff's 3rd Set of Discovery Requests electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
03/16/2023 | Response to OPSB Staff Discovery Request - Second Set electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
03/02/2023 | Response to OPSB Staff Discovery Request - First Set electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 5 |
02/24/2023 | Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
02/17/2023 | Construction Notice Application for the Fiddlestix Switch & Poston-Ross 138-kV Cut-In Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 550 |
02/13/2023 | In the Matter of Pre-application Notification Letter for the Fiddlestix Switch & Poston-Ross 138-kV Cut-In Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 3 |