05/09/2023
|
Notice of Construction Completion electronically filed by Ms. Devan K. Flahive on behalf of AmericanTransmission Systems Incorporated. |
03/10/2023
|
Notice of Construction Start for East Akron-Evans 138 kV Transmission Line Switches Installation Project electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated. |
02/16/2023
|
Service Notice - Staff Report. |
02/16/2023
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
01/18/2023
|
Response to First Set of Data Requests from Staff electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
12/16/2022
|
Construction Notice Application for the East Akron-Evans 138kV Transmission Line Switches Installation Project electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated. |
12/06/2022
|
In the Matter of the Pre-Application Notification Letter for the East Akron-Evans 138 kV Transmission Line Switches Installation Project electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |