Date Filed | Summary | Pages |
01/18/2024 | Service Notice. | 3 |
01/18/2024 | Opinion & Order issuing a certificate of environmental compatibility and public need to AEP Ohio Transmission Company, Inc. for the construction and operation of a 138-kV overhead electric transmission line in Scioto County, Ohio, subject to the conditions set forth in the stipulation and consistent with this Opinion and Order electronically filed by Ms. Mary E. Fischer on behalf of Ohio Power Siting Board. | 33 |
09/22/2023 | Transcript of Hearing held on September 7th 2023, at 10:00AM, before the Honorable Clint White and Nicholas Walstra, at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, Hearing Room 11-C, Columbus , Ohio
electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Spencer, Michael O. Mr. | 26 |
09/06/2023 | Prefiled Testimony of Robert Holderbaum on Behalf of the Staff of the Public Utilities Commission of Ohio, Power Siting Department electronically filed by Mrs. Kimberly M. Naeder on behalf of OPSB. | 6 |
09/06/2023 | Prefiled Testimony of Alicia Cross in Support of the Stipulation and Recommendation electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 8 |
09/06/2023 | Stipulation and Recommendation for the Althea-Sweetgum Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 12 |
08/31/2023 | Service Notice. | 2 |
08/31/2023 | Administrative Law Judge Entry ordering that the joint motion be granted and that all testimony be submitted by September 6, 2023 electronically filed by Ms. Donielle M. Hunter on behalf of Nicholas J. Walstra, Administrative Law Judge, Ohio Power Siting Board. | 4 |
08/30/2023 | Joint Motion for Extension and Memorandum in Support electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.. | 5 |
08/18/2023 | Transcript of Public Hearing Held 8/8/23 at 5:00 p.m. electronically filed by Litigation Support on behalf of Public Utilities Commission of Ohio. | 21 |
07/26/2023 | Service Notice. | 3 |
07/26/2023 | Notice of Proof of Compliance with Service and Public Distribution Requirements and Second Notices Sent electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 9 |
07/24/2023 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 49 |
07/13/2023 | Notice of Proof of Compliance Clarification with the Althea-Sweetgum 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
07/11/2023 | Response to OPSB Staff's 9th Set of Discovery Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 59 |
06/15/2023 | Proof of Compliance Letter electronically filed by Hector Garcia-Santana on behalf of AEP OhioTransmission Company, Inc. | 29 |
05/26/2023 | Service Notice. | 2 |
05/26/2023 | Administrative Law Judge Entry ordering that the effective date of the application be May 26, 2023, that the hearings in this matter be scheduled at the times and places designated in Paragraphs 11 and 12, that notices of the application and hearings be published by Applicant in accordance with Paragraphs 14 and 15 and that the parties observe the filing deadlines set forth in Paragraph 16 electronically filed by Debbie S. Ryan on behalf of David M. Hicks, Administrative Law Judge, Ohio Power Siting Board. | 6 |
05/03/2023 | Responses to Ohio Power Siting Board Staff's 7th Set of Discovery Requests electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 6 |
05/01/2023 | Responses to Staff's 8th Data Request electronically filed by Hector Garcia-Santana on behalf of AEP OhioTransmission Company, Inc. | 304 |
04/24/2023 | Response to Staff's 6th Set of Data Request electronically filed by Hector Garcia-Santana on behalf of AEP OhioTransmission Company, Inc. | 4 |
04/14/2023 | Correspondence regarding Proof of Payment electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 3 |
03/23/2023 | Notice of Proof of Compliance with Notification Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 12 |
03/10/2023 | Correspondence Letter regarding Application completeness electronically filed by Robert A. Holderbaum on behalf of PUCO Staff. | 3 |
03/09/2023 | Response to Staff's 5th Set of Discovery Requests electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
03/01/2023 | TransCo Response to Staff's 3rd Set of Interrogatories electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 9 |
02/27/2023 | Response to Staff's Discovery Request Set 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 4 |
02/27/2023 | Response to Staff's Discovery Request Set 1 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 3 |
02/21/2023 | Responses to Fourth Set of Discovery Requests electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 10 |
01/12/2023 | Application - Part 5 of 5 - Althea-Sweetgum 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 121 |
01/12/2023 | Application - Part 4 of 5 - Althea-Sweetgum 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 550 |
01/11/2023 | Application - Part 3 of 5 - Althea-Sweetgum 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 200 |
01/11/2023 | Application - Part 2 of 5 - Althea-Sweetgum 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 185 |
01/11/2023 | Application - Part 1 of 5 - Cover Page for Althea-Sweetgum 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 4 |
10/21/2022 | Notice of Proof of Compliance with the Notice Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |
10/05/2022 | In the Matter of the Pre-Application Notification Letter for the Althea-Sweetgum 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 3 |