DIS - Case Record for 22-0564-EL-BNR Skip to main content
      
      
CASE NUMBER: 22-0564-EL-BNR
CASE DESCRIPTION: Lima – Fort Wayne 138 kV Transmission Tie-Lines into Gomer Station Project
DOCUMENT SIGNED ON: 5/7/2024
DATE OF SERVICE: ________________________________________
06/27/2023 Notification of In-Service Date electronically filed by Hector Garcia-Santana on behalf of AEP OhioTransmission Company, Inc.
10/25/2022 Proof of Compliance with Condition (3), Lima - Fort Wayne electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
09/01/2022 Service Notice. Staff Report
09/01/2022 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
06/15/2022 Notice of Proof of Compliance with the Notice Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
06/09/2022 Construction Notice, Lima-Fort Wayne Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
06/02/2022 In the Matter of the Pre-Application Notification Letter for the Lima - Fort Wayne 138kV Transmission Tie-Lines into Gomer Station Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.