08/23/2023
|
Notification of In-Service Date for the Cartwright 138 kV Switch Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
02/02/2023
|
Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
10/12/2022
|
Notice of Updated Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
10/05/2022
|
Notice of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
02/18/2022
|
Service Notice - Staff Report. |
02/18/2022
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
01/28/2022
|
Notice of Adjustment electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/29/2021
|
In the Matter of the Construction Notice for the Cartwright 138kV Switch Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |