10/11/2022
|
Notification of Construction Completion electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
02/07/2022
|
Construction Start Notice electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
01/28/2022
|
Service Notice. |
01/28/2022
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
01/06/2022
|
Supplemental Response to Second Set of Data Requests from OPSB Staff electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
12/22/2021
|
Response to OPSB Staff's Second Set of Data Requests electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
12/16/2021
|
Supplemental Response of American Transmission Systems, Incorporated to First Set of Data Requests from OPSB Staff electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
11/30/2021
|
American Transmission Systems, Incorporated's Responses to First Set of Data Requests from OPSB Staff electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
11/30/2021
|
Proof of Publication and Public Notice Letters for Project electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
11/12/2021
|
Letter of Notification Application for the Delta-Wauseon 138 kV Transmission Line Tap to Winameg Area Substation Project electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
11/04/2021
|
In the Matter of American Transmission Systems, Incorporated's Pre-Application Notification Letter electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems, Incorporated. |