04/29/2021
|
Proof of Compliance with Condition and associated exhibit for the Anguin Extension No. 4 138 kV Transmission Line electronically filed by Tanner Wolffram on behalf of Ohio Power Company |
04/16/2021
|
Notice Proof of Compliance associated exhibits for the Anguin Extension No. 4 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
03/30/2021
|
Service Notice. |
03/30/2021
|
Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB. |
03/18/2021
|
Notice of Supplemental Information and Associated Exhibits for the Anguin Extension No. 4 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
03/15/2021
|
Construction Notice Application for the Anguin Extension No. 4 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
03/01/2021
|
In the Matter of the Pre-Application Notification Letter for the Anguin Extension No. 4 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |