DIS - Case Record for 21-0173-EL-BLN Skip to main content
      
      
CASE NUMBER: 21-0173-EL-BLN
CASE DESCRIPTION: Windsor Extension (OH) 138 kV Transmission Line Project
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
11/02/2023 In Service Date electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
01/31/2023 Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/22/2022 Start of Construction Notice electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
05/25/2021 Service Notice
05/25/2021 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
03/17/2021 Notice: Proof of Compliance associated exhibits for the Windsor Extension (OH) 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
03/02/2021 Letter of Notification Application for the Windsor Extension (OH) 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
02/22/2021 In the Matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.