11/02/2023
|
In Service Date electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
01/31/2023
|
Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
12/22/2022
|
Start of Construction Notice electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
05/25/2021
|
Service Notice |
05/25/2021
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
03/17/2021
|
Notice: Proof of Compliance associated exhibits for the Windsor Extension (OH) 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
03/02/2021
|
Letter of Notification Application for the Windsor Extension (OH) 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
02/22/2021
|
In the Matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |