11/24/2020
|
Start of Construction Notice for the Amendment #2 to the Ginger Switch-Vigo 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
11/19/2020
|
Service Notice. |
11/19/2020
|
Opinion & Order granting the application filed by AEP Ohio Transmission Company, Inc. to amend its certificate electronically filed by Ms. Mary E. Fischer on behalf of Ohio Power Siting Board. |
10/30/2020
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
08/21/2020
|
Notice of Proof of Compliance and associated exhibits for the Ginger Switch-Vigo 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
08/14/2020
|
In the matter of the Second Amendment Application for the Ginger Switch - Vigo 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |