06/02/2021
|
Notification of Completion of Construction and In-Service Date electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. |
05/21/2020
|
Service Notice. |
05/21/2020
|
Opinion & Order approving the accelerated applications in the above-captioned proceedings for certificates to construct various transmission line projects and for a natural gas pipeline reroute project. electronically filed by Ms. Mary E Fischer on behalf of Ohio Power Siting Board. |
05/08/2020
|
Duke Energy Ohio, Inc. Letter Accepting Condition for Approval electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. |
05/08/2020
|
Service Notice |
05/08/2020
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
05/07/2020
|
Correspondence of Duke Energy Ohio, Inc.'s Response to Staff Data Request 03-001 electronically filed by Carys Cochern on behalf of Duke Energy. |
04/13/2020
|
Duke Energy Ohio, Inc.'s Response to Staff Data Request 02-002 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. |
04/13/2020
|
Duke Energy Ohio, Inc.'s Response to Staff Data Request 02-001 electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. |
03/27/2020
|
Duke Energy Ohio, Inc. Response to Staff Data Request No. 1 electronically filed by Dianne Kuhnell on behalf of Duke Energy Ohio, Inc. and Rocco D'Ascenzo and Kingery, Jeanne W. |
02/25/2020
|
Proof of Publication of the Duke Energy Ohio, Inc. Port Union to Mulhauser Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy. |
02/25/2020
|
Correspondence of Revised Proof of Service for the Duke Energy Ohio, Inc. Port Union to Mulhauser Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy. |
02/24/2020
|
Proof of Service for the Duke Energy Ohio, Inc. Port Union to Mulhauser Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy. |
02/21/2020
|
Application of Duke Energy Ohio, Inc. Port Union to Mulhauser Rebuild Project-Part 2 electronically filed by Carys Cochern on behalf of Duke Energy. |
02/21/2020
|
Application of Duke Energy Ohio, Inc. Port Union to Mulhauser Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy. |
02/18/2020
|
Duke Energy Ohio, Inc. Revised Pre-Filing Application Notification electronically filed by Ms. Emily Olive on behalf of Duke Energy Ohio and D'Ascenzo, Rocco O. Mr. and Kingery, Jeanne W. Ms. and Vaysman, Larisa M. Ms. |
02/13/2020
|
In the Matter of the Pre-Application Letter for the Port Union to Mulhauser Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc. |