11/04/2024
|
Public Comments Regarding the Project. |
10/15/2024
|
Notice of Certificate Compliance with Condition 9 – 2024 Third Quarter Complaint Summary
Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
08/12/2024
|
Public Comment of Carmen San electronically filed by Docketing Staff. |
08/09/2024
|
Public Comment of Carmen San electronically filed by Docketing Staff. |
08/09/2024
|
Public Comment of Karen Kindel and Dan Cavlina. |
08/09/2024
|
Public Comment Carmen San electronically filed by Docketing Staff. |
07/22/2024
|
Public Comment of James Reed. |
07/15/2024
|
Certificate Compliance Condition 9 – 2024 Second Quarter Complaint Summary Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
05/21/2024
|
Public Comment of Carmen San. |
04/15/2024
|
Notice of Certificate Compliance Condition 9 – 2024 First Quarter Complaint Summary Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
03/25/2024
|
Notice of Certificate of Compliance with Condition 3 – As-built Drawings electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
03/20/2024
|
Public Comment of T Young electronically filed by Docketing Staff. |
03/20/2024
|
Notice of Ownership Change, electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
03/15/2024
|
Public Comment Regarding the Project. |
03/11/2024
|
Public Comment Regarding the Project. |
03/08/2024
|
Public Comment of T. Young electronically filed by Docketing Staff. |
02/26/2024
|
Correspondence regarding Certificate Compliance Condition 3 – As-built Specifications electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
02/26/2024
|
Public Comment of T. Young electronically filed by Docketing Staff. |
02/15/2024
|
Public Comment Regarding the Project electronically filed by Docketing Staff. |
01/30/2024
|
Notice - Certificate Compliance Condition 5 – Construction Completion and Start of Facility Operations electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
01/17/2024
|
Public Comment Regarding the Project electronically filed by Docketing Staff. |
01/16/2024
|
Notice of Certificate Compliance Condition 9 – 2023 Fourth Quarter Complaint Summary
Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
01/11/2024
|
Public Comment Regarding the Project, electronically filed by Docketing Staff. |
12/21/2023
|
Service Notice. |
12/21/2023
|
Entry granting the joint application to transfer and assign a portion of the Certificate of Environmental Compatibility and Public Need issued on January 21, 2021, from Madison Fields Solar Project, LLC to American Transmission Systems, Inc. electronically filed by Debbie S. Ryan on behalf of Ohio Power Siting Board. |
12/07/2023
|
Notice - Certificate Compliance Condition 9 – Start of Operations Notice electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/15/2023
|
Public Comment Regarding the Project electronically filed by Docketing Staff. |
11/06/2023
|
Notice of Certificate Compliance Condition 8 – Operations and Maintenance Structure electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/27/2023
|
Joint Application to Transfer Certificate for Interconnecting Switchyard electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/16/2023
|
Notice of Certificate Compliance Condition 9 – 2023 Third Quarter Complaint Summary
Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
09/06/2023
|
Notice - Certificate Compliance Condition 1 – Updated Stormwater Pollution Prevention
Plan electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
08/15/2023
|
Notice of Certificate Compliance Condition 19 – Road Use and Maintenance
Agreement Amendment electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/25/2023
|
Public Comment Regarding the Project. |
07/17/2023
|
Notice of Certificate Compliance with Condition 9 – 2023 Second Quarter Complaint Summary
Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/14/2023
|
Public Comment of T Young electronically filed by Docketing Staff. |
07/07/2023
|
Notice of Certificate Compliance Condition 19 Update – Road Use and Maintenance Agreement electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
05/11/2023
|
Public Comment of T. Young. |
04/17/2023
|
Notice of Certificate Compliance Condition 9 Complaint Resolution Quarterly Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
04/03/2023
|
Public Comment Regarding the Project. |
03/16/2023
|
Public Comment of Scott A. Shearer, PH.D., P.E. Professor and Chair of The Ohio State University Department of Food, Agriculture and Biological Engineering. |
03/02/2023
|
Notice of Certificate Compliance with Condition 8 – Updated Access Road Engineering Drawing electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
02/10/2023
|
Certificate Compliance Condition 8 – Updated Access Road Drawing electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
02/06/2023
|
Public Comment Regarding the Project. |
01/13/2023
|
Notice of Certificate Compliance Condition 9 – Complaint Resolution Quarterly Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
01/05/2023
|
Public Comment Regarding the Project. |
12/01/2022
|
Public Comment Regarding the Project. |
11/30/2022
|
Notice of Certificate Compliance Condition 1 – Emergency Response Plan electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/29/2022
|
Notice of Certificate Compliance Condition 13 – Landscape and Lighting Plan electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/28/2022
|
Correspondence Compliance with Condition 19 - Road Use and Maintenance Agreement electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/28/2022
|
Certificate Compliance Condition 6 and Application – National Pollutant Discharge Elimination System Permit electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/21/2022
|
Notice of Certificate Compliance Condition 9 – Complaint Resolution Plan and Construction Notice Letters electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/01/2022
|
Certificate Compliance Condition 1 – Stormwater Pollution Prevention Plan electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/01/2022
|
Certificate Compliance Condition 1 – Spill Prevention, Control, and Countermeasure Plan electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/28/2022
|
Notice of Certificate Compliance Condition 8 – Part 2 - Updated Engineering Drawings Memorandum electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/28/2022
|
Notice of Certificate Compliance Condition 8 – Updated Engineering Drawings electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/28/2022
|
Notice of Certificate Compliance Amendment Condition 2 – Fence Design electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/28/2022
|
Notice of Certificate Compliance Condition 19 – Traffic Plan electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/27/2022
|
Notice of Compliance with Condition 2 – Preconstruction Conference Agenda electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/27/2022
|
Certificate Compliance Condition 15 – Sound Level Assessment Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/20/2022
|
Notice of Compliance with Condition 1 – Material Safety Data Sheets electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/17/2022
|
Public Comment Regarding the Project, via website, electronically filed by Docketing Staff. |
10/14/2022
|
Notice of Compliance with Condition 5 – Construction Start Date – December 5, 2022 electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/14/2022
|
Notice of Compliance with Amendment Condition 2 – Perimeter Fence Detail electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/14/2022
|
Notice of Compliance with Condition 1 and Amendment Condition 1 – Final Glint and Glare Analysis electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/14/2022
|
Notice of Compliance with Condition 1 – Equipment Data Sheets and TCLP Test electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/06/2022
|
Notice of Withdrawal of Counsel electronically filed by Ms. Leah Curtis on behalf of Ohio Farm Bureau Federation. |
09/30/2022
|
Notice of Compliance with Condition 8 – Engineering Drawings electronically filed by Christine M.T. Pirie on behalf of Madison Fields Solar Project, LL. |
09/30/2022
|
Notice of Compliance Amendment with Condition 3 – Rosedale Bible Institute Protection Zone electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
09/30/2022
|
Notice of Compliance with Condition 8 – Geotechnical Engineering Report electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
09/30/2022
|
Notice of Compliance with Condition 1 – Decommissioning Plan electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
03/17/2022
|
Public Comment Regarding the Project. |
03/17/2022
|
Public Comment Regarding the Project. |
11/09/2021
|
Certificate Compliance Condition 10 – Interconnection Service Agreement and
Interconnection Construction Service Agreement electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/22/2021
|
Public Comment of Concerned Citizen, via website, electronically filed by Docketing Staff. |
03/22/2021
|
Public Comment of Anthony Sasson, via website, electronically filed by Docketing Staff. |
01/21/2021
|
Service Notice. |
01/21/2021
|
Opinion & Order issuing a certificate to Madison Fields Solar subject to the conditions set forth in the stipulation and consistent with this Opinion, Order and Certificate. electronically filed by Ms. Mary E Fischer on behalf of Ohio Power Siting Board. |
12/31/2020
|
Transcript for hearing held on 12/17/20 before Ms. Megan Addison and Mr. Matthew Sandor, Administrative Law Judges, Ohio Power Siting Board, via Webex, electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Gibson, Karen Sue Mrs. |
12/16/2020
|
Transcript (AMENDED) for hearing in the matter of the application of Madison Fields Solar Project, LLC held on 12/03/20 at 6:00 p.m. before Administrative Law Judges Ms. Megan Addison and Mr. Matthew Sandor and OPSB Director Mary Mertz via Webex electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mrs. Karen Sue Gibson. |
12/14/2020
|
Steve Taylor Public Testimony Exhibit 3 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mrs. Karen Sue Gibson. |
12/14/2020
|
Steve Taylor Public Testimony Exhibit 2 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mrs. Karen Sue Gibson. |
12/14/2020
|
Steve Taylor Public Testimony Exhibit 1 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mrs. Karen Sue Gibson. |
12/14/2020
|
Madison Fields Testimony Summary of Cathy Cowan Becker on behalf of Simply Living in Conjunction with the Ohio Sustainable Business Council electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mrs. Karen Sue Gibson. |
12/14/2020
|
Madison Fields DCA Public Hearing Testimony Summary and Exhibits of Anthony Sasson on behalf of Darby Creek Association electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mrs. Karen Sue Gibson. |
12/14/2020
|
Madison Fields DCA Public Hearing Testimony Summary of Anthony Sasson on behalf of Darby Creek Association electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mrs. Karen Sue Gibson. |
12/14/2020
|
Transcript for hearing held on 12/03/20 at 6:00 p.m. before Administrative Law Judges Ms. Megan Addison and Mr. Matthew Sandor and OPSB Director Mary Mertz via Webex electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mrs. Karen Sue Gibson. |
12/09/2020
|
Public Comment of Steve Taylor, via website, electronically filed by Docketing Staff. |
12/09/2020
|
Prefiled Testimony of Matthew Butler on Behalf of the Staff of the Public Utilities Commission of Ohio Power Siting Department electronically filed by Mrs. Kimberly M Naeder on behalf of OPSB. |
12/09/2020
|
Public Comment of T Young (additional information), via website, electronically filed by PUCO Staff. |
12/09/2020
|
Public Comment of T Young, via website, electronically filed by PUCO Staff. |
12/09/2020
|
Testimony of Lauren Devine electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
12/09/2020
|
Joint Stipulation and Recommendation electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
12/07/2020
|
Service Notice |
12/07/2020
|
Administrative Law Judge Entry granting OFBF’s motion to intervene and ordering that Madison Fields’ motion for extension of its testimony due date be granted and that Madison Fields file its expert and factual testimony on or before December 9, 2020.
electronically filed by Kelli C. King on behalf of Matthew Sandor, Administrative Law Judge, Ohio Power Siting Board. |
12/07/2020
|
Motion for Extension of Testimony Due Date for Applicant Request for an Expedited Ruling and Memorandum in Support electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
12/04/2020
|
Public Comment of Tyler M. Duvelius via website electronically filed by Docketing Staff. |
12/03/2020
|
Public Comment of Concerned Consumer, via website, electronically filed by Docketing Staff. |
12/02/2020
|
Correspondence Witness List for 12/3/20 Local Public Hearing electronically filed by Ms. Mary E Fischer on behalf of Ohio Power Siting Board. |
11/25/2020
|
Proof of Second Publication and Service of Procedural Schedule and Accepted, Complete Application electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/24/2020
|
Public Comment of Anonymous Consumer, via website, electronically filed by PUCO Docketing. |
11/20/2020
|
Public Comment of Jon Showalter, via website, electronically filed by Docketing Staff. |
11/18/2020
|
Service Notice. (Staff Report) |
11/18/2020
|
Motion to Intervene and memorandum in support of Ohio Farm Bureau Federation electronically filed by Amy M Milam on behalf of Ohio Farm Bureau Federation. |
11/18/2020
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
11/13/2020
|
Supplemental Responses to the Third and Fourth Data Requests from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/04/2020
|
Response to Fourth Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/23/2020
|
Response to OPSB Staff's Third Data Request electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/19/2020
|
Proof of Publication and Service of Procedural Schedule and Accepted, Complete Application electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/02/2020
|
Response to Second Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
09/28/2020
|
Service Notice. |
09/28/2020
|
Administrative Law Judge Entry establishing new procedural schedule electronically filed by Kelli C. King on behalf of Anna Sanyal, Administrative Law Judge, Public Utilities Commission of Ohio. |
09/28/2020
|
Response to First Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
09/17/2020
|
Notice of Application Fee Paid electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
09/17/2020
|
Certificate of Service of Accepted, Complete Application on Local Public Officials and Libraries electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
09/15/2020
|
Correspondence regarding application completeness electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
08/25/2020
|
Public Comment of Gregg Jess, via website, electronically filed by Docketing Staff. |
08/03/2020
|
Supplement to Application SHPO Archaeological Concurrence Letter electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/23/2020
|
Notice - Updated Application Exhibit W – Phase I Archaeological Survey electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/20/2020
|
Proof of Pub for Fourth Public Information Meeting electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Confidential document target: Application filed by C.Pirik on behalf of Madison Fields Solar Project, LLC. (5 pages) |
07/17/2020
|
Motion for Protective Order and Memorandum in Support electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Application - Part 8 of 8 (Exhibits U - Z) electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Application - Part 7 of 8 (Exhibits R - T) electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Application - Part 6 of 8 (Exhibits N - Q) electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Application - Part 5 of 8 (Exhibit M) electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Application - Part 4 of 8 (Exhibit L) electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Application - Part 3 of 8 (Exhibits B - K) electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Application - Part 2 of 8 (Figures 08-7 - 08-8 and Exhibit A) electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/17/2020
|
Application - Part 1 of 8 (Text and Figures 03-1 - 08-6) electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
07/16/2020
|
Public Comment of Toni Young, via website, electronically filed by Docketing Staff. |
06/24/2020
|
Notice of Compliance with Service Requirement for Fourth Public Information Meeting electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
06/24/2020
|
Third Preapplication Notification Letter/
Fourth Public Information Meeting electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
06/23/2020
|
Service Notice. |
06/23/2020
|
Attorney Examiner Entry As such, Madison Fields should schedule a fourth public information meeting as soon as possible and provide notice of such meeting to the public. We further direct Madison Fields to keep Board Staff apprised of all details related to the fourth public information meeting and be prepared to provide any information upon request. electronically filed by Kelli C King on behalf of Anna Sanyal, Attorney Examiner, Public Utilities Commission of Ohio. |
06/22/2020
|
Public Comment of Toni Young, via website, electronically filed by Docketing Staff. |
06/19/2020
|
Notice of Supplement to PIM service notice. electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
06/11/2020
|
Notice of Compliance with Service Requirement for Third Public Information Meeting electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
06/11/2020
|
Proof of Publication for Third Public Information Meeting electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
05/29/2020
|
Second Pre-application Notification Letter/
Third Public Information Meeting electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
05/22/2020
|
Service Notice |
05/22/2020
|
Administrative Law Judge Entry granting motions for waivers as detailed herein. electronically filed by Ms. Mary E Fischer on behalf of Megan J. Addison, Administrative Law Judge, Ohio Power Siting Board. |
05/13/2020
|
Public Comment of Toni Young electronically filed by Docketing Staff. |
05/04/2020
|
Correspondence Letter of No Objection electronically filed by Mrs. Kimberly M. Naeder on behalf of OPSB. |
04/30/2020
|
Public Comment submitted via web of Toni Young electronically filed by Docketing Staff. |
04/28/2020
|
Motion for Waiver and Request for Approval to Hold a Virtual Public Information Meeting Request for Expedited Ruling and Memorandum in Support electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
11/18/2019
|
Public Comment of Jonathan Francis, Chairman, Madison Soil & Water Conservation District, via website electronically filed by Docketing Staff. |
11/07/2019
|
Public Comment of Brianna Taylor via website electronically filed by Docketing Staff. |
11/04/2019
|
Public Comment of Steve Taylor via website electronically filed by Docketing Staff. |
11/04/2019
|
Public Comment of Sarah Chandler via website electronically filed by Docketing Staff. |
10/28/2019
|
Proof of Pub for Public Information Meetings electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. (Madison County) |
10/23/2019
|
Motion for Waiver and Memorandum in Support electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/23/2019
|
Notice of Compliance with Service Requirement electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |
10/18/2019
|
In the matter of the Preapplication Notification Letter electronically filed by Christine M.T. Pirik on behalf of Madison Fields Solar Project, LLC. |