DIS - Case Record for 18-1125-EL-REN Skip to main content
      
      
CASE NUMBER: 18-1125-EL-REN
CASE DESCRIPTION: Michigan Public Power Agency
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
03/05/2020 Case Action Form closing case with an effective date of 3/5/2020.
01/15/2020 Finding & Order that the Commission denies the certification application of Beebe 1B Wind Facility as an eligible Ohio renewable energy resource generating facility electronically filed by Docketing.
01/15/2020 Service Notice
10/28/2019 Staff Review and Recommendation electronically filed by Mr. Stuart M Siegfried on behalf of PUCO Staff.
05/08/2019 Michigan Public Power Agency's Responses to Ohio Public Utilities Commission Request for Additional Information electronically filed by Patrick J. Devon on behalf of Michigan Public Power Agency.
11/16/2018 Response Michigan Public Power Agency responses to Ohio Public Utilities Commission questions regarding Beebe 1B Wind Project REN Application. electronically filed by Patrick J Devon on behalf of MICHIGAN PUBLIC POWER AGENCY.
10/17/2018 Service Notice
10/17/2018 Attorney Examiner Entry suspending the automatic approval process of the application and ordering applicant to respond to Commission staff's inquiry within 30 days electronically filed by Ms. Mary E Fischer on behalf of Richard M. Bulgrin, Attorney Examiner, Public Utilities Commission of Ohio.
09/04/2018 In the Matter of the Application of Beebe 1B for Certification as an Eligible Ohio Renewable Energy Resource Generating Facility electronically filed by Patrick J. Devon on behalf of Beebe 1B Renewable Energy, LLC and Michigan Public Power Agency.