05/13/2019
|
Letter stating that these Projects were completed on May 1, 2019 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. |
10/01/2018
|
Notice that the preconstruction conference with OPSB Staff was held on September 24, 2018 and that start of construction will begin on approximately January 2, 2019 filed by N. Bryksenkova on behalf of FirstEnergy Service Company. |
10/05/2017
|
Request to reopen case filed by J. Agranoff. |
10/05/2017
|
Case Action Form Closing Case effective 9/25/17 electronically filed by Michelle A Green on behalf of Public Utilities Commission of Ohio. |
08/17/2017
|
Service Notice |
08/17/2017
|
Opinion, Order, and Certificate ordered, That the Stipulation be approved and adopted. It is, further, ordered, That certificate be issued to ATSI for the construction, operation, and maintenance of the transmission facility along the preferred route, subject to the conditions set forth in the Stipulation and this Order. |
07/13/2017
|
Transcript for hearing held on June 27, 2017 before Jay Agranoff, administrative judge, at the Public Utilities Commission of Ohio electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Spencer, Michael O. Mr. |
07/13/2017
|
PUCO Exhibit Filing, staff exhibit 1 &2; joint exhibit 1; Applicant exhibit 2 & 3. |
06/23/2017
|
Joint Stipulation and Recommended Findings of Fact and Conclusions of Law by Applicant, ATSI, and Staff of OPSB electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
06/21/2017
|
Testimony of James S. O'Dell electronically filed by Mrs. Tonnetta Y. Scott on behalf of PUCO. |
06/16/2017
|
Testimony of Ms. Nataliya Bryksenkova in support of the issuance of a Certificate of Environmental Compatibility and Public Need. electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
06/14/2017
|
Transcript in the Matter of the Application of American Transmission Systems, Incorporated for a Certificate of Environmental Compatibility and Public Need for the Construction of the East Springfield-Tangy 138kV Loop to Broadview Substation Project, hearing held on June 12, 2017. electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Burke, Carolyn. |
06/05/2017
|
Notice of Issues for Cross-Examination at Adjudicatory Hearing electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
06/01/2017
|
Proof of Pub of Second Public Notice of Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
05/30/2017
|
Service Notice |
05/30/2017
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
04/28/2017
|
Notification of Public Information Meeting electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
04/28/2017
|
Notice of Service of First Public Notice of Accepted and Complete Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
04/12/2017
|
Administrative Law Judge Entry ordering hearings in this matter be scheduled at the times and places designated in paragraph (5); that the application and hearings be noticed by ATSI in accordance with paragraphs (7) and (8); that Staff file its Staff Report pursuant to paragraph (9); and that the parties file their issue lists and testimony in accordance with paragraph (9). Entry electronically filed by Debra Hight on behalf of Jay S. Agranoff, Administrative Law Judge. |
04/12/2017
|
Service Notice |
03/27/2017
|
Affidavit of Proof of Service of complete application on Public Officers filed by Nataliya Bryksenkova on behalf of FirstEnergy Service Company. |
03/14/2017
|
OPSB Chair Letter Regarding Compliance electronically filed by Mr. James S. O'Dell on behalf of Power Siting Staff. |
02/21/2017
|
Letter of ATSl stating that will be conducting habitat evaluation and considering best practices to avoid adversely affecting the stated federally listed species identified filed by N. Bryksenkova on behalf of FirstEnergy Service Company. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 9 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 8 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 7 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 6 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 5 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 4 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 3 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 2 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
01/13/2017
|
Application for the East Springfield-Tangy 138kV Loop to Broadview Substation Project (Part 1 of 9) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
10/25/2016
|
Service Notice |
10/24/2016
|
Administrative Law Judge Entry granting ATSI's motion for waiver; electronically filed by Vesta R Miller on behalf of Jeffrey R. Jones, Administrative Law Judge, Ohio Power Siting Board |
10/21/2016
|
Proof of Pub of Notice of Public Information Meeting in Springfield News Sun electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
10/21/2016
|
Motion for Partial Limited Waiver of Pre-Application Notification Letter Filing Date and Memorandum in Support electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
10/21/2016
|
In the matter of the pre-application Notification Letter concerning Public Information Meeting electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |