08/09/2019
|
Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. |
02/09/2017
|
Notification of Start of Construction and In-Service Date for the Raider 138 kV Extension Project
electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
07/11/2016
|
Correspondence -Accepting all of the Staff Recommended Conditions electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
07/08/2016
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. |
06/28/2016
|
Notification (Public Notification Compliance Filing) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
06/28/2016
|
Notification: Compliance Filing electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
06/23/2016
|
Notice (Construction Notice) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
06/16/2016
|
In the matter of the Pre-Application- Letter of Notification, electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |