07/15/2015
|
Letter of notification that the North Medina- West Akron project was completed on approximately 5/21/15, filed by J. Thacker on behalf of FirstEnergy Service Company. |
02/10/2015
|
Letter in response to letter of notification that project will begin the week of February 9, 2015 filed on behalf of FirstEnergy Service Company by J. Thacker.
|
01/22/2015
|
Proof of publication in the Medina Gazette of the Notice of Proposed Major Utility Facility filed on behalf of American Transmission Systems, Inc. by R. Schmidt, Jr. |
12/30/2014
|
Notice of Acceptance of Proposed Staff Conditions and Supplement to Application electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
12/23/2014
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
11/20/2014
|
Supplemental Information and Construction Access Map electronically filed by Ms. Jessica L Thacker on behalf of FirstEnergy Service Company. |
10/01/2014
|
In the matter of the Letter of Notification North Medina-West Akron 138kV Transmission Line Tap to Laurel Substation Project filed by Jesssica Thacker on behalf of FirstEnergy Service Company. |