07/31/2015
|
Memorandum indicating the project has been put in service and the case may be closed. |
07/31/2015
|
Case Action Form closing case effective 7/30/2015. |
02/13/2015
|
Notification electronically filed by Mrs. Vicki B Sowder on behalf of CSX Transportation. |
10/27/2014
|
Memorandum stating that the Ohio Rail Development Commission, CSX Transportation, Inc., and the Village of Columbus Grove entered into a letter of agreement that project has been recommended - filed by J. Henry PUCO Staff. |
04/09/2014
|
Service Notice |
04/09/2014
|
Finding & Order adopting and approving stipulation; that by July 9, 2014 CSX submit to the Commission's Railroad Division site plans and cost estimates for the projects, and by July 16, 2014, file a letter in this docket advising that site plans and cost estimates have been submitted to the
Commission; that CSX; that CSX proceed with and complete the projects on or before April 9, 2015; that CSX notify Staff of any changes in the scope of work, cost overruns, materials, etc., |
03/14/2014
|
In the matter of a request for a consolidation project in the Village of Columbus Grove, Putnam County, Ohio. |
|