08/05/2015
|
Notice that the overall project was placed in service on approximately May 1, 2015 filed by T. Krauss on behalf of First Energy Service Company. |
05/16/2014
|
Letter serving as notice of an engineering design change filed by T. Krauss on behalf of FirstEnergyService Company. |
04/15/2014
|
Status report for the three referenced projects filed by T. Krauss on behalf of FirstEnergy Service Company. |
02/26/2014
|
Notice of Acceptance of Staff's Proposed Conditions on Certificate electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
02/20/2014
|
Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB |
02/06/2014
|
In the matter of the Notice of Construction of The Cloverdale – Harmon #2 69 kV Transmission Line Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |