09/13/2019
|
Case Action Form to Close Case with and effective date of 9/13/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Administrative Law Judge, The Ohio Power Siting Board. |
06/27/2018
|
Notification of In-Service and Construction Complete Dates electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
02/21/2017
|
Notification of Start of Construction for the Biers Run-Circleville 138 kV Transmission Line Project
electronically filed by Mrs. Erin C. Miller on behalf of AEP Ohio Transmission Company. |
02/15/2017
|
Notice of Start of Construction for the Biers Run-Circleville 138 kV Transmission Line Project
electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. |
10/21/2015
|
Letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
10/13/2015
|
Response electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
03/09/2015
|
Opinion and Order that the stipulation be approved and adopted, that a certificate be issued to AEP for the construction, operation, and maintenance of the transmission facility along the preferred route, subject to the conditions set forth in the Stipulation and Order. |
03/09/2015
|
Service Notice |
01/09/2015
|
Public Comment filed by G. Dunlap. |
01/07/2015
|
Public Comment Response to G. Dunlap from M. Butler, OPSB staff. |
12/10/2014
|
Transcript in the matter of AEP Ohio Transmission Company hearing held on 11/21/14 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Gibson, Karen Sue Mrs. |
11/21/2014
|
PUCO Exhibit filing: Sign-in sheets. |
11/21/2014
|
Transcript in the matter of AEP Ohio Transmission Company hearing held on 11/06/14 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Spencer, Michael O. Mr. |
11/20/2014
|
PUCO Exhibit Filing. |
11/20/2014
|
Transcript in the matter of AEP Ohio Transmission Company hearing held on 11/05/14 electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Spencer, Michael O. Mr. |
11/19/2014
|
Prefiled Testimony of Jon C. Pawley submitted by Assistant Attorney General John Jones on behalf of the Staff of the Ohio Power Siting Board. electronically filed by Kimberly L Keeton on behalf of Ohio Power Siting Board. |
11/14/2014
|
Pre-filed Testimony of Shawn P. Malone in Support of the Joint Stipulation and Recommendation electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
11/14/2014
|
Joint Stipulation and Recommendation electronically filed by Mr. Matthew . Satterwhite on behalf of AEP Ohio Transmission Company. |
11/07/2014
|
Public comment regarding the proposed route for the Biers Run-Circleville Transmission Line Project filed by consumer Chris Mullins. |
11/07/2014
|
Service Notice |
11/07/2014
|
Administrative Law Judge Entry that the motion for an extension of time be granted, and that the adjudicatory hearing be rescheduled in accordance with Finding (4); electronically filed by Debra Hight on behalf of Jay S. Agranoff, Administrative Law Judge. |
11/07/2014
|
Correspondence electronically filed by Mr. Matthew J Satterwhite on behalf of AEP Ohio Transmission Company. |
11/04/2014
|
Motion for Extension of time to file testimony and Memorandum in Support electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
10/31/2014
|
Proof of Pub -Biers Run-Circleville electronically filed by Mr. Steven T Nourse on behalf of AEP Ohio Transmission Company. |
10/29/2014
|
Correspondence Issues List of AEP Ohio Transco electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
10/23/2014
|
Service Notice |
10/21/2014
|
Staff Report of Investigation electronically filed by Mrs. Yvonne W Cooper on behalf of Staff of OPSB. |
10/15/2014
|
Correspondence enclosing Supplement to the Application filed on June 2, 2014 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
10/08/2014
|
Proof of Notification electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
10/01/2014
|
Proof of Pub of Biers-Run Circleville 138 kV Transmission Line Project electronically filed by Mr. Yazen Alami on behalf of Ohio Power Company. (Franklin County) |
09/05/2014
|
Service Notice |
09/05/2014
|
Administrative Law Judge Entry that the hearings in this matter be scheduled and notices of the application and hearings be published by AEP electronically filed by Debra Hight on behalf of Jay S. Agranoff, Administrative Law Judge. |
08/15/2014
|
Correspondence of August 15th enclosing Proof of Service electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
08/01/2014
|
Letter regarding compliance and review of application filed by T. Johnson, OPSB Board. |
06/02/2014
|
Application Biers Run – Circleville 138 kV Transmission Line Project Part 7 of 7 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
06/02/2014
|
Application Biers Run – Circleville 138 kV Transmission Line Project Part 6 of 7 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
06/02/2014
|
Application Biers Run – Circleville 138 kV Transmission Line Project Part 5 of 7 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
06/02/2014
|
Application Biers Run – Circleville 138 kV Transmission Line Project Part 4 of 7 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
06/02/2014
|
Application Biers Run – Circleville 138 kV Transmission Line Project Part 3 of 7 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
06/02/2014
|
Application Biers Run – Circleville 138 kV Transmission Line Project Part 2 of 7 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
06/02/2014
|
Application Biers Run – Circleville 138 kV Transmission Line Project Part 1 of 7 electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |
12/31/2013
|
Public comment response letter to Union-Scioto Local School District from K. Wissman, OPSB. |
11/26/2013
|
Comment letter from Z-Acres Farms LLC regarding the Biers Run Circleville Line project |
11/05/2013
|
Response to The Eugene Mace Family filed by K.Wissman on behalf of OPSB. |
10/24/2013
|
Response to Byron P. Gearhart filed by K.Wissman on behalf of OPSB. |
10/11/2013
|
Proof of Pub for the Biers Run Circleville Line Project electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. (Ross and Pickaway Counties) |
09/30/2013
|
In the matter of the Pre-Application Notification Letter electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. |