CASE NUMBER: 12-2223-EL-BNR
CASE DESCRIPTION: BAYSHORE-DECANT 138 KV TRANSMISSION LINE RELOCATION FOR THE OREGON DITCH PROJECT
DOCUMENT SIGNED ON: 8/31/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
01/17/2013 Letter in response to the Construction Notice project filed on August 3, 2012 filed by Travis M. Turner on behalf of Energy Delivery Transmission and Substation Design FirstEnergy Service Company.
11/19/2012 Letter stating that construction for the Oregon Ditch project is expected to begin on approximately November 19, 2012 filed by T. Turner on behalf of FirstEnergy Service Company.
08/29/2012 Staff Investigation Report and Recommendation filed by OPSB Staff.
08/03/2012 In the matter of the construction notice of American Transmission Systems, Incorporated for the Bayshore-Decant 138 kV Transmission Line Relocation for the Oregon Ditch Project.