DIS - Case Record for 12-2205-RR-FED Skip to main content

Case Record For:

12-2205-RR-FED

File a Public Comment
Case Title: WHEELING AND LAKE ERIE RAILWAY
Status: CL-CLOSED
Industry Code: RR-RAILROAD
Purpose Code: FED-Federally funded warning projects
Date Opened: 8/1/2012
Date Closed: 12/11/2014
Printable Docket Card Service List
View per page
Date FiledSummaryPages
12/11/2014Case Status Form to close case. 1
12/11/2014Memo to close cases filed by PUCO Staff. 1
10/30/2014Service Notice2
10/30/2014Attorney Examiner Entry that WLE’s request for an extension of time to complete the project is granted in accordance with finding 5; and that WLE complete the project by November 30, 2014; electronically filed by Debra Hight on behalf of Scott E. Farkas, Attorney Examiner.3
10/29/2014Staff recommends that the Commission grant this request filed by PUCO. 1
10/28/2014Request to extend deadline for project 60 days filed by T. Andrews on behalf of Wheeling & Lake Erie Railway Company.1
10/27/2014Request to extend the deadline for project filed by T. Andrews on behalf of Wheeling & Lake Erie Railway Company.1
09/10/2014Service Notice2
09/10/2014Entry ordering that WLE's request for an extension of time to complete the project is granted in accordance with finding (4).2
09/02/2014Request to extend the deadline until October 31 filed by T. Andrews on behalf of W&LE Railway Company.1
08/29/2014Response to the request for extension of time filed by G. Martin, PUCO Staff.1
08/29/2014Request for extension of time filed by T. Andrews on behalf of Wheeling & Lake Erie Railway Company.1
08/15/2014Signed request for extension of time for project plus attachments filed by T. Andrews on behalf of Wheeling & Lake Erie Railway Company.6
08/14/2014Service Notice2
08/14/2014Attorney Examiner Entry granting WLE's request for an extension to complete the project by 09/17/2014 - electronically filed by Sandra Coffey on behalf of Scott Farkas, Attorney Examiner, Public Utilities Commission of Ohio.3
08/13/2014Request of Wheeling & Lake Erie Railway for a 60 day extension of time to complete a corridor project in the City of Canton, stark County filed by PUCO Staff.3
08/13/2014Request from Wheeling & Lake Erie Railway Company requesting an extension of 60 days for this project filed by T. Andrews.1
03/14/2014Correspondence stating that the second request for extension can be disregarded in its entirety filed by PUCO Rail Staff, G. Martin on behalf of D. Reinsel of Wheeling and Lake Erie Railway.1
03/13/2014Request for extension of time filed by D. Reinsel on behalf of Wheeling & Lake Erie Railway Company.5
03/12/2014Service Notice2
03/12/2014Entry ordered, that WLE's request for an extension of time to complete the project in granted, in accordance with Finding (4). It is, further, ordered, that WLE complete the project by August 17, 2014. 2
02/27/2014Service Notice2
02/27/2014Attorney Examiner Entry grants WLE's request for an extension of time to complete the project by 03/19/2014. - electronically filed by Sandra Coffey on behalf of Scott Farkas, Attorney Examiner, Public Utilities Commission of Ohio3
02/20/2014Letter requesting an extending of the deadline filed by D.Reinsel on behalf of Wheeling & Lake Erie Railway Company. 4
02/20/2014Letter stating that due to the fact that the City portion of this project is beyond the control of WE, staff recommends that the Commission grant this request filed by PUCO Staff, G. Martin.5
02/18/2014Request to extend the deadline for project to provide Local Highway Authority, City of Canton additional time to complete their portion filed on behalf of Wheeling & Lake Erie Railway Company by D. Reinsel.4
11/16/2012Letter stating that AEP, installation work to be completed by 12/14/2012 filed by D. Reinsel on behalf of Wheeling & Lake Erie Railway Company. (FAX)1
10/16/2012Letter filed by PUCO Staff G. Martin1
08/15/2012Service Notice1
08/15/2012Finding and order stating that by September 14, 2012, W&LE file a notice that it has initiated with OPC, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossings as set forth in finding 3; W&LE follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the projects by February 17,2014.4
08/01/2012In the matter of the Wheeling & Lake Erie Railway safety corridor & traffic signal preemption project in Stark County, City of Canton.6