12-2051-EL-ORD

Case Title: IN THE MATTER OF THE COMMISSIONS REVIEW OF CHAPTER 4901:1-22 OHIO ADMINISTRATIVE CODE REGARDING INTERCONNECTION SERVICES
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: ORD-Administrative order
Date Opened: 7/11/2012
Date Closed: 2/1/2016
Printable Docket Card Service List
View per page
Date FiledSummaryPages
02/01/2016Memo closing cases with an effective date of 2/1/16 electronically filed by Richard M. Bulgrin on behalf of Public Utilities Commission of Ohio.2
08/15/2014Notice of Withdrawal of Counsel by the Office of the Ohio Consumers' Counsel electronically filed by Patti Mallarnee on behalf of Yost, Melissa Ms.3
07/23/2014Notice of Withdrawal of Counsel electronically filed by Mr. Nicholas A. McDaniel on behalf of Environmental Law and Policy Center.3
12/05/2013Service Notice86
12/04/2013Finding and order stating that attached amended Rules 4901:1-22-01 through 4901:1-22-13 O.A.C., be adopted and filed with the Joint Committee on Agency Rule Review, the Secretary of State and the Legislative Service Commission, in accordance with Divisions (D) and (E) of Section 111.15, Revised Code.89
10/15/2013Notice of substitution of Counsel electronically filed by Mrs. Kimberly W. Bojko on behalf of Ohio Manufacturers' Association2
10/15/2013Notice of withdrawal electronically filed by Teresa Orahood on behalf of J. Thomas Siwo, Bricker & Eckler LLP.3
02/07/2013Supplemental Reply Comments of the Environmental Law and Policy Center, Ohio Environmental Council, Solar Energy Industries Association, and Vote Solar Initiative electronically filed by Mr. Nicholas A. McDaniel on behalf of Environmental Law and Policy Center and Ohio Environmental Council and Solar Energy Industries Association and Vote Solar Initiative.6
02/07/2013Supplemental Reply Comments of Ohio Edison Company, Cleveland Electric Illuminating Company, and Toledo Edison Company electronically filed by Mr. Robert M. Endris on behalf of Burk, James W. Mr.7
02/07/2013Reply Comments electronically filed by Teresa Orahood on behalf of Ohio Hospital Association.2
02/07/2013Supplemental reply comments of the Interstate Renewable Energy Council, Inc. on staff's proposed modifications to the interconnection services and standards electronically filed by Mr. Thad B Culley on behalf of Interstate Renewable Energy Council, Inc.13
02/07/2013Reply comments of Fosdick & Hilmer, Inc filed by James Landers P.E on behalf of Fosdick & Hilmer Inc. 2
02/06/2013Supplemental Reply Comments of Duke Energy Ohio, Inc. electronically filed by Carys Cochern on behalf of Watts, Elizabeth H. Ms.8
01/31/2013Initial Supplemental Comments electronically filed by Mr. Matthew J Satterwhite on behalf of Ohio Power Company.9
01/31/2013Supplemental Comments of OE-CEI-TE electronically filed by Mr. Robert M. Endris on behalf of Mr. James W. Burk.14
01/31/2013Comments on the Commission's Review of Chapter 4901:1-22, Ohio Administrative Code, Regarding Supplemental Proposed Interconnection Rule Changes electronically filed by Eric R Brown on behalf of The Dayton Power and Light Company.7
01/31/2013Comments on the Standby Rate proposals within Case 12-2051-EL-ORD electronically filed by Mr. Clifford Haefke on behalf of Energy Resources Center.5
01/31/2013Comments of the Environmental Law & Policy Center, Ohio Environmental Council, Solar Energy Industries Associations, and Vote Solar Initiative electronically filed by Mr. Nicholas A. McDaniel on behalf of Environmental Law and Policy Center and Ohio Environmental Council and Solar Energy Industries Association and Vote Solar Initiative.6
01/31/2013Supplemental comments of the Interstate Renewable Energy Council, Inc., on staff's further proposed modifications to interconnection services and standards electronically filed by Mr. Thad B Culley on behalf of Interstate Renewable Energy Council, Inc.6
01/31/2013Supplemental Comments by the Office of the Ohio Consumers' Counsel electronically filed by Patti Mallarnee on behalf of Yost, Melissa Ms.6
01/31/2013Supplemental Comments of Interstate Gas Supply, Inc electronically filed by Mr. Matthew White on behalf of IGS Energy.7
01/31/2013Supplemental comments filed by James Landers P.E on behalf of Fosdick & Hilmer, Inc. 3
01/31/2013Supplemental Comments of Duke Energy Ohio, Inc. electronically filed by Carys Cochern on behalf of Watts, Elizabeth H. Ms.5
01/30/2013Comments of the OMA Energy Group electronically filed by Teresa Orahood on behalf of OMA Energy Group.6
01/16/2013Service Notice30
01/16/2013Entry ordering that all interested persons or entities wishing to file supplemental comments with the Commission on the proposed rule changes do so no later than January 31, 2013, and file supplemental reply comments by February 7, 2013.14
01/02/2013Return Mail.1
01/02/2013Return Mail.1
12/17/2012Comments of Duke Energy Ohio, Inc. electronically filed by Dianne Kuhnell on behalf of Duke Energy Ohio, Inc. and Spiller, Amy B. and Watts, Elizabeth H.6
12/17/2012Motion to File Comments Instanter by Duke Energy Ohio, Inc. and Memorandum in Support electronically filed by Dianne Kuhnell on behalf of Duke Energy Ohio, Inc. and Spiller, Amy B. and Watts, Elizabeth H.3
12/05/2012Comments of Metro CD Engineering, LLC on proposed modifications to interconnection services and standards electronically filed by Mr. Scotte Elliott on behalf of Metro CD Engineering, LLC.59
12/04/2012Reply Comments by the Office of the Ohio Consumers' Counsel electronically filed by Patti Mallarnee on behalf of Yost, Melissa Ms.10
12/04/2012Reply Comments electronically filed by Ms. Carrie M. Dunn on behalf of The Cleveland Electric Illuminating Company and Ohio Edison Company and The Toledo Edison Company.11
12/04/2012Reply Comments of Interstate Renewable Energy Council, Inc. on Proposed Modifications to Interconnection Services and Standards electronically filed by Mr. Thad B Culley on behalf of Interstate Renewable Energy Council, Inc.6
11/20/2012Comments in regard to the commission's review of chapter 4901:1-22 electronically filed by Mr. David R Blair on behalf of GEM Energy and Mr. David R Blair2
11/19/2012Comments filed by J. Karlak, an interested party.4
11/19/2012Comments of Recycled Energy Development filed by R. Muson. 2
11/19/2012Comments on the Commission's Review of Chapter 4901:1-22, Ohio Administrative Code, Regarding Interconnection Service electronically filed by Eric R Brown on behalf of The Dayton Power and Light Company.5
11/19/2012Comments electronically filed by Ms. Carrie M Dunn on behalf of The Cleveland Electric Illuminating Company and Ohio Edison Company and The Toledo Edison Company.7
11/19/2012Comments of Interstate Gas Supply Inc. electronically filed by Mr. Matthew White on behalf of IGS Energy.5
11/19/2012Comments by the Office of the Ohio Consumers' Counsel electronically filed by Patti Mallarnee on behalf of Yost, Melissa Ms.14
11/19/2012Comments of the Interstate Renewable Energy Council, Inc. on Proposed Modifications fo Interconnection Services and Standards electronically filed by Mr. Thad B Culley on behalf of Interstate Renewable Energy Council, Inc.14
11/19/2012Comments of Labyrinth Management Group, Inc. and Mr. Lance Traves on PUCO Proposed Changes to OAC 4901:1-22 electronically filed by Mr. Lance S Traves on behalf of Labyrinth Management Group, Inc.10
11/19/2012Initial Comments of Ohio Power Company electronically filed by Mr. Steven T Nourse on behalf of Ohio Power Company.10
11/19/2012Comments of Cleveland Thermal, LLC and its Subsidiaries electronically filed by Mr. Samuel C. Randazzo on behalf of Cleveland Thermal, LLC.6
11/19/2012Comments in regards to the Commissions review of Chapter 4901:1-22 filed by D.R.Blair, P.E. Senior Vice President. ( FAX ) 1
11/16/2012Comments filed by J. Landers on behalf of Fosdick & hilmer, Inc.20
10/18/2012Service Notice22
10/17/2012Entry ordered, that all interested persons or entities wishing to file comments with the Commission on the proposed rule changes and business impact analysis do so no later than November 19, 2012, and file reply comments by December 4, 2012.45
07/17/2012Service Notice14
07/16/2012Entry ordering in accordance with Finding (6), a workshop be scheduled for August 17, 2012, at 10:00 a.m., at the offices of the Commission, 180 East Broad Street, Hearing Room 11-B, Columbus, Ohio 43215. (BAM)4
07/11/2012In the Matter of the Commission's Review of Chapter 4901:1-22, Ohio Administrative Code, Regarding Interconnection Services.1