03/20/2015
|
Case Action Form to Close Cases effective 3/20/2015. |
11/05/2012
|
Response letter to the Construction Notice on the Kirby-Tangy Transmission Line Project filed by D. Parks, FirstEnergy Service Company. |
06/26/2012
|
Staff investigation report and recommendation filed on behalf of PUCO. |
05/23/2012
|
In the matter of the application of Construction Notice Kirby-Tangy 138 kv Transmission Line Tap to consolidated Electric's South Scioto Substation filed by David W. Parks on behalf of FirstEnergy Service Company.
|