Case Record For: 12-1430-EL-BLN File a Public Comment Case Title: TOLEDO EDISON Status: CL-CLOSED Industry Code: EL-ELECTRIC Purpose Code: BLN-letter of notification Date Opened: 4/30/2012 Date Closed: 3/20/2015 Case Documents Public Comments Parties of Record Related Cases Printable Docket Card Service List View per page Date FiledSummaryPages 03/20/2015Case Action Form to Close Cases effective 3/20/2015.6 01/24/2013Letter stating that the construction on Delta-Wauseon 138 kV Transmission Line Tap to Linde BOC Substation project was completed on approximately January 18, 2013 filed by T. Turner on behalf of FirstEnergy Service Company.1 07/23/2012Letter stating that the project is expected to begin on approximately July 30, 2012 filed by T. Turner on behalf of FirstEnergy Service Company.1 06/26/2012Staff investigation report and recommendation filed on behalf of PUCO.1 04/30/2012In the matter of the letter of notification of the Delta-Wauseon 138kV Transmission Line tap to Linde Boc Substation.30