03/28/2019 | Case Action Form closing case with an effective date as of 3/28/19. | 1 |
02/15/2017 | Notice of Start of Construction and In-Service Date for the Biers Run Substation Project electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company. | 2 |
11/17/2014 | Notice of Withdrawal of Counsel electronically filed by Mrs. Tonnetta Y Scott on behalf of Mr. Devin D Parram. | 3 |
06/05/2014 | Notice sent to Shawn Malone filed by K. Lambeck on behalf of OPSB. | 1 |
10/16/2013 | Notice of Commencement of Construction electronically filed by Mr. Yazen Alami on behalf of AEP Ohio Transmission Company. | 2 |
09/30/2013 | Opinion and Ordered, That AEP Transco's motion seeking approval of public notification be granted. | 22 |
09/30/2013 | Service Notice | 2 |
07/09/2013 | Transcript in the matter of AEP Ohio Transmission Company, Inc. hearing held on 06/25/13 , before Jay S. Agranoff, Administrative Law Judge,at the Public Utilities Commission of Ohio, 180 East Broad St, Columbus, Ohio, Room 11D electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Sloas, Valerie J. Mrs. | 18 |
06/26/2013 | Transcript in the matter of AEP Ohio Transmission Company, Inc. hearing held on 06/11/13 at the Pioneer School for Developmental Disabilities, 11268 County Road 550, Chillicothe, Ohio electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Sloas, Valerie J. Mrs. | 22 |
06/14/2013 | Direct Testimony of Shawn Malone electronically filed by Erin C. Miller on behalf of AEP Ohio Transmission Company, Inc. | 5 |
06/14/2013 | Joint Stipulation and Recommendation electronically filed by Erin C. Miller on behalf of AEP Ohio Transmission Company, Inc. | 14 |
06/13/2013 | Proof of Pub - Biers Run Substation Project in the Chilicothe Gazette electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 4 |
06/10/2013 | Letter of Notification -Proof of Notification to Property or Land Owners electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 8 |
05/30/2013 | Response: List of issues on behalf of AEP Ohio Transmission Company electronically filed by Erin C. Miller on behalf of AEP Ohio Transmission Company, Inc. | 2 |
05/29/2013 | Motion for Waiver from OAC Rule 4906-5-08(C)(3) and Memorandum In Support electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 7 |
05/23/2013 | Staff Report of investigation electronically filed by Mr. Adam S Bargar on behalf of Staff of OPSB. | 38 |
04/15/2013 | Proof of Pub Biers Run Substation Project (Chillicothe Gazette) Ross County electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 4 |
03/22/2013 | Service Notice | 1 |
03/22/2013 | Administrative Law Judge Entry scheduling local public hearing on June 11, 2013, at 6:00 p.m., and adjudicatory hearing on June 25, 2013, at 10:00 a.m., electronically filed by Vesta R Miller on behalf of Jay S. Agranoff, Administrative Law Judge, Ohio Power Siting Board. | 5 |
03/22/2013 | Receipt of check received from AEP Ohio Trans Co. dated 3/13/2013. | 1 |
03/21/2013 | Notice Proof of Service electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 14 |
02/13/2013 | Response letter sent to Mr. Shawn P. Malone filed by T. A. Snitchler, Chairman on behalf of OPSB | 2 |
12/20/2012 | Application for a Certificate of Environmental Compatibility and Public Need/Biers Run Station filed by S. Moore. on behalf of AEP Ohio Transmission Co., Inc. | 170 |
07/05/2012 | Proof of Pub for Biers Run Substation Project electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 4 |
06/12/2012 | Notice of rescheduled Public Informational Meeting electronically filed by Erin C. Miller on behalf of AEP Ohio Transmission Company, Inc. | 2 |
05/22/2012 | Letter of Notification Pre-Application electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc. | 4 |
04/25/2012 | In the matter of the application for a Certificate of Environmental Compatibility and Public Need for a 345/138/69 kV Biers Run Substation Project. electronically filed by Erin C. Miller on behalf of AEP Ohio Transmission Company, Inc. | 2 |