03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
10/16/2012 Letter of notification informing the Commission that the construction on the Clark Substation Expansion Project was completed on approximately June 1, 2012 filed on behalf of FirstEnergy Service Company by J. Toth.
03/28/2012 Letter of Notification that the construction of the Clark Substation Expansion Project will begin the week of April 2, 2012 and that notice will be provided once the project has been completed filed by John T. Toth on behalf of FirstEnergy Service Company.
03/19/2012 Staff investigation report and recommendation.
02/27/2012 In the matter of the application/letter of notification of American Transmission Systems, Incorporated for the Clark Substation Expansion Project.