DIS - Case Record for 11-5836-EL-BLN Skip to main content
      
      
CASE NUMBER: 11-5836-EL-BLN
CASE DESCRIPTION: AMERICAN TRANSMISSION SYSTEMS, INCORPORATED A SUBSIDIARY OF FIRSTENERGY CORP
DOCUMENT SIGNED ON: 11/21/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
06/05/2012 Letter of notification that the Lime City Substation Project was completed on May 24, 2012 filed by J. Thacker on behalf of FirstEnergy Service Company.
02/09/2012 Letter stating that construction of Lime City Substation Capacitor Bank Addition Project will begin on Wednesday, February 8th, 2011 filed by J. Thacker on behalf of FirstEnergy Service Company.
02/06/2012 Letter stating that the construction for the Lime City Substation Capacitor Bank Addition Project will begin on or shortly after February 20, 2011 filed by J. Thacker on behalf of FirstEnergy Service Company.
01/25/2012 Staff report and recommendation.
11/30/2011 In the matter of the letter of notification - Lime City Substation Capacitor Bank Addition Project.
11/30/2011 Letter of notification of the Lime City Substation Capacitor Bank Addition Project filed by American Transmission Systems Incorporated.