DIS - Case Record for 11-4805-EL-BLN Skip to main content
      
      
CASE NUMBER: 11-4805-EL-BLN
CASE DESCRIPTION: Yellow Creek 138 kV Extension
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
03/02/2012 Notice of completion of Yellow Creek 138k V Line Extension electronically filed by Erin C Miller on behalf of AEP Ohio Transmission Company, Inc.
09/29/2011 Notice of Intent to Start Construction at the Yellow Creek location on October 6, 2011 electronically filed by Erin C Miller on behalf of American Electric Power.
09/19/2011 OPSB Staff report of Investigation recommending approval of project Yellow Creek 138 KV Transmission Line Extension filed by J. Pawley.
08/30/2011 In the matter of the American Electric Power Company's letter of notification for expedited approval for the Yellow Creek 138 kV Extension that is expected to begin in October 2011 .