Date Filed | Summary | Pages |
08/11/2014 | Correspondence that Beaver to Brownhelm Junction 345 kV Transmission Line Project was completed approximately 4/1/2014 filed by S. Humphrys on behalf of First Energy. | 1 |
03/26/2014 | Letter of Notification that the Beaver to Brownhelm Junction 345 kV Transmission Line Project began commercial operation March 8, 2014 filed on behalf of FirstEnergy service Company by S. Humphrys. | 1 |
04/01/2013 | Notification to the PUCO Staff of the next phase of the construction activities on the Project commence filed by Scott M. Humphrys on behalf of FirstEnergy Services Company. | 1 |
03/11/2013 | Service Notice | 2 |
03/11/2013 | Opinion, Order, and Certificate stating that the Stipulation is approved and adopted and that a certificate be issued to ATSI for the construction, operation, and maintenance of the project on the preferred transmission line route. | 26 |
02/01/2013 | Transcript of American Transmission Systems, Inc. hearing held on 01/17/13 Before Scott Farkas, Administrative Law Judge, held at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, Hearing Room 11-A, Columbus, Ohio electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. and Spencer, Michael O. Mr. | 21 |
02/01/2013 | PUCO Exhibit filing for hearing held 1/17/13. | 50 |
01/15/2013 | Stipulation of the Parties and Recommended Conditions electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 21 |
01/10/2013 | Transcript for hearing held on 1/3/13 before Mr. Scott Farkas, Administrative Law Judge, held at the Brownhelm Township Hall, 1940 North Ridge Road, Vermilion, Ohio, electronically filed by Mrs. Jennifer Duffer on behalf of Armstrong & Okey, Inc. | 15 |
01/04/2013 | Testimony of Scott Humphrys on Behalf of Applicant American Transmission Systems, Incorporated electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated. | 21 |
12/27/2012 | Notice of Prehearing Statement of Issues electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated | 6 |
12/20/2012 | Service Notice | 3 |
12/20/2012 | Proof of Pub for Lorain County - Public Information Meeting electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 5 |
12/19/2012 | Staff Report Filed electronically filed by Mr. Grant T. Zeto on behalf of Staff of the Ohio Power Siting Board. | 41 |
12/19/2012 | Proof of publication for the County of Lorain filed by R. Schmidt on behalf of ATSI. | 5 |
12/11/2012 | Proof of Pub Affidavit of Proof of Mailing of Notification Letters and Supporting Documents, electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. | 33 |
12/07/2012 | Response to Data Requests with Clarification of Common Route electronically filed by Mr. Grant T Zeto on behalf of Staff of the Ohio Power Siting Board. | 13 |
11/09/2012 | Proof of Pub for Lorain County filed by R. Schmidt Jr. on behalf of ATSI. | 5 |
10/18/2012 | Service Notice | 2 |
10/17/2012 | Administrative Law Judge Entry ordered the hearings in this matter be scheduled at the times and places designated in Finding (5); the notices of the application and hearings be published by ATSI in accordance with Findings (7) and (8); that Staff file its Staff Report pursuant to Finding (9); and that all parties file their issues lists, and expert and factual testimony in accordance with Finding (9). - electronically filed by Sandra Coffey on behalf of Scott Farkas, Attorney Examiner, Public Utilities Commission of Ohio. | 5 |
10/12/2012 | Affidavit of Proof of Service of Complete and Accepted Application on Local Officials electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. | 3 |
10/03/2012 | Letter informing the Commission to the correction of a minor typographical error that occurred in the
compliance letter for this case, filed on September 27, 2012 filed by Staff. | 1 |
09/27/2012 | Letter informing Mr. Parke that the application filed with the Ohio Power Siting Board has been found to comply with Chapters 4906-01, et seq., of the Ohio Administrative Code (OAC) filed by Staff. | 2 |
09/11/2012 | Service Notice | 2 |
09/11/2012 | Entry by Administrative Law Judge granting ATSI's waiver requests. - electronically filed by Sandra Coffey on behalf of Scott Farkas, Attorney Examiner, Public Utilities Commission of Ohio | 4 |
08/30/2012 | Letter of Notification electronically filed by Mrs. Tonnetta Y Scott on behalf of PUCO. | 2 |
08/17/2012 | Supplement continued. (part 3 of 3) | 52 |
08/17/2012 | Supplement continued . (part 2 of 3) | 201 |
08/17/2012 | Supplement to the application. (Part 1 of 3) | 202 |
08/15/2012 | Amendment to Motion for Waiver electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated. | 4 |
08/09/2012 | Motion For Certain Waivers and Memorandum in Support electronically filed by Ms. Catherine Darcy Copeland on behalf of American Transmission Systems, Incorporated | 9 |
07/31/2012 | Application For A Certificate of Environmental Compatibility and Public Need Beaver to Brownhelm Junction 345 kV Transmission Line Construction Project filed by Scott Humphrys on behalf FirstEnergy Service Company. | 194 |
08/15/2011 | In the matter of the pre-application notification for Beaver-Davis Besse # 2 345 kV Transmission Line Project filed on behalf of FirstEnergy Service Company by S. Humphrys. | 1 |