DIS - Case Record for 10-2885-EL-BLN Skip to main content
      
      
CASE NUMBER: 10-2885-EL-BLN
CASE DESCRIPTION: BAYSHORE IRONVILLE 138KV TRANSMISSION INTERMEDIATE STRUCTURE PLACEMENT PROJECT
DOCUMENT SIGNED ON: 11/22/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
04/28/2011 Letter in response to notification on the Bayshore-Ironville 138 k V Transmission Line Intermediate Structure, project completed April 24, 2011 filed on behalf of FirstEnergy by J. Thacker.
04/20/2011 Letter notifying the Commission that construction on this project will begin on or shortly after April 22, 2011 filed by J. Thacker on behalf of FirstEnergy Service Company.
01/27/2011 Ohio Power Siting Board Staff investigation report and recommendation.
01/26/2011 Letter of notification supplement regarding the Bayshore-Ironville 138 kV Transmission Intermediate Structure Placement Project previously filed on November 30, 2010, filed by J. Thacker on behalf of FirstEnergy Service Company.
12/02/2010 In the matter of the letter of notification-Bayshore-Ironville 138 kV Transmission Intermediate Structure Placement Project.