DIS - Case Record for 10-1452-EL-BNR Skip to main content

Case Record For:

10-1452-EL-BNR

Case Title: PLEASANT VALLEY WEST AKRON WEST 138 KV TRANSMISSION LINE TAP TO CLEVELAND CLINIC DATA CENTER SUBSTATION PROJECT
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 9/30/2010
Date Closed: 3/20/2015
Printable Docket Card Service List
View per page
Date FiledSummaryPages
03/20/2015Case Action Form to Close Cases effective 3/20/2015.6
08/11/2011Letter in response to the Construction Notice filed September 30, 2010 and approval on September 30, 2010 filed by J. Thacker on behalf of FirstEnergy Service Company.1
02/22/2011Letter in response to the construction notice, that construction will begin on or about February 16, 2011, filed by J. Thacker on behalf of FirstEnergy Service Company.1
01/06/2011Staff investigation report and recommendation filed by Staff. 1
12/03/2010Letter to J. Toth approving the request to resume the Board's review of the construction notice of the Pleasant Valley-West Akron project filed by K. Wissman, OPSB.1
11/22/2010Construction notice Pleasant Valley-West 138 kV Transmission Line Tap to Cleveland Clinic Data Center Substation Project filed by J. Toth on behalf of FirstEnergy Service Company.1
11/08/2010Letter stating that the request to suspend the Board's review for this Construction Notice is hereby granted filed by. Staff. 1
11/08/2010Letter respectfully requesting an indefinite suspension of the OPSB staff review for the Construction Notice filed on September 29, 2010 for the Pleasant Valley-West Akron 138kV Transmission Line Tap to Cleveland Clinic Data Center Substation Project filed by J. Toth1
11/04/2010Request of American Transmission Systems, Inc. of an indefinite suspension of the OPSB Staff Review for the Construction Notice filed on September 29, 2010 for the Pleasant Valley-West Akron 138kV Transmission Line Tap to Cleveland Clinic Data Center Substation Project, filed by J. Toth on behalf of FirstEnergy Service Company.1
09/30/2010In the matter of the construction notice for Pleasant Valley-West Akron West 138kV Transmission Line Tap to Cleveland Clinic Data Center Substation Project.11