02/04/2013 Case status form to archive case.
09/04/2012 Memo closing case with an effective date as of 9/4/12.
09/04/2012 Memo stating that the grade crossing improvements/upgrades are in-service and Staff requests that these cases be closed of record filed by PUCO Staff.
07/26/2012 Memorandum in regard to the Staff recommendation that the Attorney Examiner grant the request for extension of time until August 31, 2012 to complete the Cleveland Commercial Railroad Lines gate installation project filed by George Martin.
07/25/2012 Request of Cleveland Commercial Railroad Lines for an extension of the project completion date from July 31, 2012 to August 31, 2012 filed by Michael J. Kole.
06/28/2012 Service Notice
06/28/2012 Entry ordering CCR's request for an extension of time be granted and that CCR complete the projects by July 31, 2012. (JML)
06/27/2012 Memorandum stating that Staff recommends the Attorney Examiner to grant the request for extension of time filed on behalf of PUCO.
06/26/2012 Letter requesting an extension of the project completion date from June 30, 2012, to July 31, 2012 filed by M. Kole on behalf of Cleveland Commercial Railroad.
05/30/2012 Service Notice
05/30/2012 Entry ordering CCR's request for an extension of time be granted and that CCR complete the projects by July 2, 2012. (SF)
05/25/2012 Memo recommending the Attorney Examiner grant a 30 day extension to complete the Cuyahoga County project filed by Staff.
05/25/2012 Request submitted by Cleveland Commercial Railroad Company, LLC for an extension of the project completion date from May 31, 2012 to June 30, 2012 filed by Michael J. Kole.
04/30/2012 Entry that CCR's request for an extension of time be granted and that CCR complete the projects by May 30,2012. (SF)
04/30/2012 Request submitted by Cleveland Commercial Railroad Company, LLC for an extension of the project completion date from April 30, 2012 to May 31, 2012 filed by Michael J. Kole.
04/30/2012 Response from the PUCO Rail Division recommending approval of the the Cleveland Commercial Railroad request for extension of time.
04/30/2012 Service Notice
03/30/2012 Service Notice
03/29/2012 Memo recommending the Attorney Examiner grant an extension to complete the City of Bedford project filed by Staff.
03/29/2012 Entry ordering CCR's request for an extension of time be granted and that they complete the projects by April 30, 2012. (JML)
03/27/2012 Letter requesting an extension of the project completion date from March 31, 2012 to April 30, 2012, filed by M.J.Kole, President on behalf o f Cleveland Commercial Railroad Lines. (FAX)
02/29/2012 Service Notice
02/29/2012 Entry ordered that CCR's request for an extension of time to complete the projects be granted and CCR complete the projects by March 31, 2012. (SF)
02/28/2012 Letter supporting the extension request of Cleveland Commercial on behalf of the City of Bedford filed by Staff.
02/28/2012 Memorandum responding to the request of the Cleveland Commercial Railroad for an extension of time to complete a consolidation project in the City of Bedford, Cuyahoga County, staff recommends this extension filed by Rail staff, G. Martin.
02/28/2012 Letter requesting an extension of the project completing date from February 29, 2012 to March 31, 2012 filed by M.J. Kole, President on behalf of Cleveland Commercial Railroad Lines. (FAX)
02/02/2012 Service Notice
02/01/2012 Entry granting CCR's request for an extension of time to complete the project and to be completed by March 1, 2012. (SF)
12/16/2011 Service Notice
12/16/2011 Entry that CCR's request for an extension of time to complete the projects be granted and that CCR complete the projects by January 31, 2012. (SF)
12/12/2011 Memorandum requesting that additional request for extension be granted and is recommended by Staff filed by Rail Division Staff, G. Martin.
12/12/2011 Request from Cleveland Commercial Railroad Lines for an extension of the project completion date from December 31, 2011, to February 29, 2012 filed by M. Kole on behalf of CCR.
12/09/2011 Correspondence letter by Cleveland Commercial Railroad Company to provide the PUCO an update of the projected date of completion of this project.
09/07/2011 Notice of the projected date of completion of this project to be October 14, 2011 filed on behalf of Cleveland Commercial Railroad Company by M. Kole.
07/18/2011 Return mail receipt.
06/29/2011 Service Notice
06/29/2011 Entry ordering that OCR's request for an extension of time until December 31, 2011, to complete the projects be granted; that CCR provide monthly progress reports to staff detailing the status of the projects.
06/20/2011 Memorandum in response to request for an extension of time, Staff recommends that the Commission grant a six month extension of the deadline for CCRL filed by Staff, G. Martin.
06/16/2011 Letter of support on behalf of Ohio Rail Development Commission for Cleveland Commercial Railroad's request to modify due date for project, filed by Associate Assistant Attorney General, A Klondell.
06/02/2011 Request for an extension of the project completion date from June 30, 2011, to an unspecified open date filed by M. Kole on behalf of Cleveland Commercial Railroad Lines.
11/09/2010 Notice that CCR has initiated with CEI the process to ensure that electric service will be available at the involved grade crossings for the project, filed by M. Kole.
06/30/2010 Service Notice
06/30/2010 Entry ordering that CCR submit to the Commission and ORDC site plans and cost estimates for the projects by September 28, 2010; by October 5, 2010, CCR file a notice in this docket advising that it has submitted site plans and cost estimates; by October 28, 2010, CCR file a notice that it has initiated with CEI the process to ensure that electric service will be available at the involved grade crossings.
06/14/2010 In the matter of the authorization of the Cleveland Commercial Railroad to begin a consolidation project in the City of Bedford, Cuyahoga County.