DIS - Case Record for 10-0597-EL-BLN Skip to main content
      
      
CASE NUMBER: 10-0597-EL-BLN
CASE DESCRIPTION: FIRSTENERGY SERVICE COMPANY
DOCUMENT SIGNED ON: 4/20/2024
DATE OF SERVICE: ________________________________________
03/20/2015 Case Action Form to Close Cases effective 3/20/2015.
12/29/2010 Letter of notification of Exhibits 2B, 5B, 8A and 11A that depict engineering information from a notification submission on April 30, 2010 and approved June 28, 2010, filed by S. Humphrys on behalf of FirstEnergy Service Company.
12/29/2010 Letter informing that construction on this project was completed on approximately December 10, 2010, filed by S. Humphrys on behalf of FirstEnergy Service Company.
10/28/2010 Letter in response to the letter of notification filed on April 30, 2010, and approved June 28, 2010 indicating that construction will likely begin on October 14, 2010, filed by T. Krauss.
09/23/2010 Letter of notification advising that construction has been modified in Exhibits 2A, 5A, 11 and 12, all other structures and features of the project remain the same filed on behalf of FirstEnergy Service Company by S. Humphrys.
09/23/2010 Letter of notification advising that construction is expected to begin on or shortly after September 4, 2010 filed on behalf of FirstEnergy Service Company by S. Humphrys.
06/28/2010 Staff investigation and recommendation report filed by PUCO Staff.
06/14/2010 Supplemental engineering information on behalf of FirstEnergy, Exhibit 4A replaces Exhibit 4 submitted to the Letter of Notification on April 30,2010, filed by S. Humphrys.
05/03/2010 In the matter of the letter of notification of American Transmission Systems, Incorporated and Ohio Edison Company for the proposed project of Evergreen-Ivanhoe 138 kV Transmission Line to Marvin Group.