03/20/2015
|
Case Action Form to Close Cases effective 3/20/2015. |
04/26/2012
|
Notice that the City of Hamilton has completed construction and energized Substations No. 4, 13, and 10, filed by Randy Meyer. |
09/15/2010
|
Proposal of a schedule advancement to alleviate any delay that may be caused by winter construction filed by A. McIntire on behalf of City of Hamilton. |
04/21/2010
|
OPSB Staff investigation report and recommendation filed on behalf of the Staff of The Public Utilities Commission of Ohio. |
03/31/2010
|
Letter, with check, of the City of Hamilton for expedited treatment of letter of notification application filed by R. Meyer. |
03/31/2010
|
Application continued. (Part 3 of 3) |
03/31/2010
|
Application continued. (Part 2 of 3) |
03/31/2010
|
In the matter of the letter of notification for the City of Hamilton electric department proposed Substation No. 11 to Substation No. 10 138 kV Transmission Line Project. (part 1 of 3) |