03/20/2015
|
Case Action Form to Close Cases effective 3/20/2015. |
04/10/2013
|
Letter of Notification Line F5781 138KV Hamilton to Fairfield Rebuild electronically filed by Carys Cochern on behalf of Kingery, Jeanne W Ms., and Duke Energy. |
05/06/2010
|
Letter of notification advising that Duke Energy hereby rescinds the request for an indefinite suspension dated April 22, 2010 for the F5781 138 kV Hamilton to Fairfield Rebuild Project filed by S. Lane. |
05/03/2010
|
Staff investigation report and recommendation filed on behalf of the Staff of the Public Utilities Commission of Ohio. |
05/03/2010
|
Letter of notification - request for case ruling for the F5781 138 kV Hamilton to Fairfield Rebuild project filed by S. Lane on behalf of Duke Energy Ohio, Inc. |
04/27/2010
|
Letter requesting an indefinite suspension of the OPSB staff review filed by S. Lane on behalf of Duke Energy. |
03/05/2010
|
In the matter of the letter of notification for Line F5781 138KV Hamilton to Fairfield Rebuild. |